Schedule of I-10 Freeway Closures - January 26 - 31st.

There will be full freeway closures from today, January 26 through Thursday January 31st., said Caltrans.

Schedule of I-10 Freeway Closures - January 26 - 31st.

The California Department of Transportation (Caltrans) will continue closing the portion of the San Bernardino Freeway (I-10) in Baldwin Parkf rom January 26 to January 31st.

The California Department of Transportation (Caltrans) is closing the portions of the San Bernardino Freeway (I-10) as part of the High Occupancy Vehicle lane construction project.

Continuing Long Term Closures include the Bess Avenue Pedestrian Overcrossing and full closure of Bess Avenue pedestrian overcrossing through spring, 2013 

Here is the full schedule of closures:

Saturday, January 26
·        6 p.m. to 11 a.m. – Southbound I-605 connector to eastbound I-10.
·        7 p.m. to 10 a.m. – Northbound I-605 connectors to I-10.
·        7 p.m. to 12 p.m. – Northbound I-605 Valley Boulevard on-ramps.

Westbound I-10
·        11 p.m. to 9 a.m. – Up to 3 lanes from Puente Avenue to I-605.
·        1 a.m. to 6 a.m. – Full freeway closure from Puente Avenue to I-605.
·        3 p.m. to 11 a.m. – Frazier Street, Baldwin Park Boulevard and Francisquito Avenue on- and off-ramps.
·        11 p.m. to 11 a.m. – Francisquito Avenue on-ramp.
·        8 p.m. to 11 a.m. – Puente Avenue on-ramp.
                       
Eastbound I-10
·        11 p.m. to 10 a.m. – Up to 3 lanes from I-605 to Puente Avenue.
·        2 a.m. to 7 a.m. – Full freeway closure from I-605 to Puente Avenue.
·        9 p.m. to 10 a.m. – Connector to northbound I-605.
·        9 p.m. to 10 a.m. – Durfee Avenue on-ramp.
·        3 p.m. to 11 a.m. – Baldwin Park Boulevard on- and off-ramps.
·        11:59 p.m. to 11 a.m. – Francisquito Avenue off-ramp

Sunday, January 27
·        5 p.m. to 6 a.m. – Southbound I-605 connector to eastbound I-10.
·        6 p.m. to 6 a.m. – Northbound I-605 connectors to I-10.
·        3 p.m. to 5 a.m. – Northbound I-605 Valley Boulevard on-ramps.

Westbound I-10
·        10 p.m. to 5 a.m. – Up to 3 lanes from Puente Avenue to I-605.
·        11:59 p.m. to 4 a.m. – Full freeway closure from Puente Avenue to I-605.
·        9 p.m. to 5 a.m. – Connector to I-605.
·        3 p.m. to 6 a.m. – Frazier Street and Francisquito Avenue on- and off-ramps.
·        8 p.m. to 6 a.m. – Puente Avenue on-ramp.
Eastbound I-10
·        10 p.m. to 6 a.m. – Up to 3 lanes from I-605 to Puente Avenue.
·        1 a.m. to 5 a.m. – Full freeway closure from I-605 to Puente Avenue.
·        9 p.m. to 6 a.m. – Connector to northbound I-605.
·        9 p.m. to 6 a.m. – Durfee Avenue on-ramp.
·        7 p.m. to 7 a.m. – Frazier Street off-ramp.  
·        3 p.m. to 6 a.m. – Baldwin Park Boulevard on- and off-ramps.
·        10 p.m. to 6 a.m. – Francisquito Avenue off-ramp.

Monday, January 28 through Thursday, January 31
·        8 p.m. to 6 a.m. – Southbound I-605 connector to eastbound I-10.
·        7 p.m. to 6 a.m. – Northbound I-605 connectors to I-10.
·        8 p.m. to 5 a.m. – Northbound I-605 Valley Boulevard on-ramps.

Westbound I-10
·        9 a.m. to 3 p.m. - Frazier Street. Baldwin Park Boulevard and Francisquito Avenue on- and off-ramps.
·        9 p.m. to 5 a.m. – Up to 3 lanes from Puente Avenue to I-605.
·        11 p.m. to 4 a.m. – Full freeway closure from Puente Avenue to I-605.
·        9 p.m. to 5 a.m. – Connector to I-605.
·        7 p.m. to 6 a.m. – Frazier Street, Baldwin Park Boulevard, and Francisquito Avenue on- and off-ramps.
·        9 p.m. to 6 a.m. – Puente Avenue on-ramp.

Eastbound I-10        
·        9 a.m. to 3 p.m. – Baldwin Park Boulevard on- and off-ramps.
·        10 p.m. to 6 a.m. – Up to 3 lanes from I-605 to Puente Avenue.
·        1 a.m. to 5 a.m. - Full freeway closure from I-605 to Puente Avenue.
·        9 p.m. to 6 a.m. – Connector to northbound I-605.
·        9 p.m. to 6 a.m. – Durfee Avenue on-ramp.
·        8 p.m. to 7 a.m. – Frazier Street off-ramp.  
·        7 p.m. to 6 a.m. – Baldwin Park Boulevard on- and off-ramps.
·        10 p.m. to 6 a.m. – Francisquito Avenue off-ramp.