Politics & Government
Roswell Cuts The Ribbon On New Water Treatment Plant
The new plant will provide an additional 1.8 million gallons of water per day and save the city $11.6 million over a 20-year period.
ROSWELL, GA -- The city of Roswell on Thursday cut the ribbon on its new Water Treatment Plant, a facility that replaces its 80-year-old counterpart.
The new plant will also provide an additional 1.8 million gallons of water per day compared to previous plant.
Along with an increased water supply, the new facility is expected to save Roswell $11.6 million over a 20-year period. The savings will come from reduced water purchases from Fulton County and reduced costs to repair and refurbish the previous plantβs aging equipment.
Find out what's happening in Roswellfor free with the latest updates from Patch.
βWe are thrilled to be celebrating the grand opening of our new plant,β said Dan Skalsky, director of the city's Environmental/Public Works Department. βFor those in the water industry, the construction of a new water treatment plant is really a labor of love. Our team has poured incredible amounts of time, energy and vision into this project, and we are grateful for their hard work and dedication, which has made it all possible.β
Other benefits of the new plant include maintaining local control over a key portion of the cityβs water resources, ensuring water treatment capacity as the community grows and serving as a regional leader in responding to the governorβs call to develop additional water resources to support the metro Atlanta regionβs water supply plan.
Find out what's happening in Roswellfor free with the latest updates from Patch.
βThe opening of our new water plant is a significant and exciting milestone for the city of Roswell,β said Mayor Jere Wood. βAt a time when our nation has witnessed the critical role clean water plays in a communityβs health and well-being, this occasion is a chance for us to reflect on our cityβs long-standing history of providing quality water to our citizens while also reaffirming this commitment for generations to come.β
Construction of the new plant began in April 2014 and was managed by city staff and Layne Heavy Civil, Inc. The new plant began producing and distributing water to Roswell Water Utilityβs approximately 5,500 customers in March 2016.
The plantβs construction cost $15 million, which Roswell paid for through a 20-year loan through the Georgia Environmental Finance Authority. The loan was secured at an interest rate of 1.4 percent because of its AAA bond rating and designation as a Water First Community.
You can learn more about the new plant by clicking here.
---
Images via city of Roswell