15 Sep 2014
49° Clear
Patch Instagram photo by longunderwearman
Patch Instagram photo by quadrofoglio
Patch Instagram photo by athomeinmygarden
Patch Instagram photo by daniellemastersonbooks
Patch Instagram photo by healthandbeautynz
Patch Instagram photo by andreagazeapt
Patch Instagram photo by reh_22
Patch Instagram photo by athomeinmygarden
Patch Instagram photo by pespatchpsp

Dredging on the Hudson in Sleepy Hollow

You may have noticed some heavy equipment at work along the Hudson Line nearby.

Dredging on the Hudson in Sleepy Hollow Dredging on the Hudson in Sleepy Hollow Dredging on the Hudson in Sleepy Hollow Dredging on the Hudson in Sleepy Hollow Dredging on the Hudson in Sleepy Hollow Dredging on the Hudson in Sleepy Hollow Dredging on the Hudson in Sleepy Hollow Dredging on the Hudson in Sleepy Hollow Dredging on the Hudson in Sleepy Hollow Dredging on the Hudson in Sleepy Hollow

So you're on Metro North and you see something happening on the riverfront at the old GM plant in Sleepy Hollow, but perhaps you don’t want to read the big document from the Department of Environmental Conservation...

Here’s help from Sleepy Hollow Village Administrator Anthony Giaccio on what exactly is happening down there now and for some weeks to come.

The dredging operation, or replacement of some 1,000 yards of potentially contaminated soil from the old General Motors yard, has not begun yet. What the very dramatic looking cranes are doing, said Giaccio, are doing the preliminary protective work: installing posts, netting and sheathing.

Metal sheets will protect the edge of the GM property, basically a rock barricade adjacent to the bulkhead at the foot of Ichabod’s Landing, from collapsing when workers start scooping out dirt from the river bottom. The big posts they are installing is meant to hold up netting which will do the same protective work.

The workers are setting up red containers where they will be depositing the removed soil. Dredging is slated to begin next week and continue for the next three to four weeks through December. This will be followed, said Giaccio, by another few weeks of “dismantling” which will take the job to completion in mid-January. Or that, he said, is at least the goal.

“It did get pushed back a week because of the hurricane,” he said. If we encounter a snowstorm along the way however, that probably won’t pose any issue. Unless the river is frozen solid, the work should continue as planned.

As the dirt gets removed it will be tested on site by the DEC “to determine whether they can use it on site,” Giaccio said. If the dirt meets certain certification standards, it could potentially be used as fill in the development to come.

The tall cranes will come into use again in the end of the work to lift and remove the metal sheeting. Until then, the cranes will rest as the scooping operation continues through the holidays.

Share This Article