The city is undertaking some pavement rehabilitation and application of slurry seal work for the next four weeks at various locations throughout the city. The hours of operations will be approximately from 7 a.m. to 4 p.m., Monday-Friday. The streets affected are:
• Roadside Drive
• Lewis Road from Roadside Drive
• Rainbow View Drive
• Rainbow Hill Road
• Larboard Lane
• Reyes Adobe Road
• Slurry seal and striping of the Recreation Center parking lot at 30610 Thousand Oaks Boulevard
• Slurry seal and striping of the Park-N-Ride lots north and south of the 101 freeway and Kanan Road
Schedule for this week of July 21, 2014 through July 25, 2014 is as follows:
Monday, July 21, 2014
The contractor will be performing milling operations on the following streets Roadside Dr, Dorothy Dr, and Lewis Rd.
Tuesday, July 22, 2014
The contractor will be performing milling operations on the following streets Rainbow Hill Dr, Larboard Ln, and Rainbow View Dr.
Wednesday, July 23, 2014
The contractor will be performing milling operations on the following streets Canwood St (West of Reyes Adobe Rd), Reyes Adobe Rd (From Thousand Oaks Bl to School entrance), paving will be taking place on the following streets: Roadside Dr, Dorothy Dr, & Lewis Rd.
Thursday, July 24, 2014
The contractor will be paving the following streets: Rainbow Hill, Larboard Ln, and Rainbow View Dr.
Friday, July 25, 2014
The contractor will be paving the following streets: Canwood St & Reyes Adobe Rd (From Thousand Oaks Bl to School entrance).
Please Note: The contractor will be setting up traffic control in this area. Please use caution while driving through this area.
This ongoing schedule will be updated at the end of this week.
Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.