The California Department of Transportation (Caltrans) will close portions of the San Bernardino Freeway (I-10) as part of the High Occupancy Vehicle lane construction project. The following schedule will be in effect, weather permitting:
Continuing Long Term Closures
Bess Avenue Pedestrian Overcrossing
Full closure of Bess Avenue pedestrian overcrossing through fall, 2012
Eastbound I-10
Baldwin Park Boulevard on-ramp through December, 2012
Westbound I-10
Baldwin Park Boulevard on- and off-ramps through December, 2012
Sunday, December 2
· 11:59 p.m. to 6 a.m. – Southbound I-605 connector to eastbound I-10.
· 11:59 p.m. to 6 a.m. – Northbound I-605 connectors to I-10.
· 11:59 p.m. to 5 a.m. – Northbound I-605 Valley Boulevard on-ramps.
Westbound I-10
· 11:59 p.m. to 5 a.m. – Up to 3 lanes from Puente Avenue to I-605.
· 11:59 p.m. to 4 a.m. – Full freeway closure from Puente Avenue to I-605.
· 11:59 p.m. to 5 a.m. – Connector to I-605.
· 11:59 p.m. to 6 a.m. – Frazier Street, Baldwin Park Boulevard and Francisquito Avenue on- and off-ramps.
· 11:59 p.m. to 6 a.m. – Puente Avenue on-ramp.
Eastbound I-10
· 11:59 p.m. to 6 a.m. – Up to 3 lanes from I-605 to Puente Avenue.
· 11:59 p.m. to 5 a.m. – Full freeway closure from I-605 to Puente Avenue.
· 11:59 p.m. to 6 a.m. – Connector to northbound I-605.
· 11:59 p.m. to 6 a.m. – Durfee Avenue on-ramp.
· 11:59 p.m. to 7 a.m. – Frazier Street off-ramp.
· 11:59 p.m. to 6 a.m. – Baldwin Park Boulevard on- and off-ramps.
· 11:59 p.m. to 6 a.m. – Francisquito Avenue off-ramp.
Monday, December 3 through Thursday, December 6
· 8 p.m. to 6 a.m. – Southbound I-605 connector to eastbound I-10.
· 7 p.m. to 6 a.m. – Northbound I-605 connectors to I-10.
· 8 p.m. to 5 a.m. – Northbound I-605 Valley Boulevard on-ramps.
Westbound I-10
· 9 a.m. to 3 p.m. - Frazier Street. Baldwin Park Boulevard and Francisquito Avenue on- and off-ramps.
· 9 p.m. to 5 a.m. – Up to 3 lanes from Puente Avenue to I-605.
· 11 p.m. to 4 a.m. – Full freeway closure from Puente Avenue to I-605.
· 9 p.m. to 5 a.m. – Connector to I-605.
· 7 p.m. to 6 a.m. – Frazier Street, Baldwin Park Boulevard, and Francisquito Avenue on- and off-ramps.
· 9 p.m. to 6 a.m. – Puente Avenue on-ramp.
Eastbound I-10
· 9 a.m. to 3 p.m. – Baldwin Park Boulevard on- and off-ramps.
· 10 p.m. to 6 a.m. – Up to 3 lanes from I-605 to Puente Avenue.
· 1 a.m. to 5 a.m. - Full freeway closure from I-605 to Puente Avenue.
· 9 p.m. to 6 a.m. – Connector to northbound I-605.