Albert Webb of Lies: Feasibility Study

Brian Knoll from Webb & Associates Lies about his own Fraudulent Sewer Feasibility Study

On January 22, 2018 the City of Beaumont along with Brian Knoll from Albert Webb & Associates presented a workshop slideshow on why the City can impose a Sewer Fee Increase without Voter Approval.

Brian Knoll’s slideshow contained Webb & Associates’ Feasibility Study’s Option #1 and Option #2 Cost Estimate Comparisons. The January 22, 2018 slideshow included Recycled Water and listed the following Feasibility Study Cost Estimates:

Option #1 Total Project Costs: $100,650,000

Find out what's happening in Banning-Beaumontfor free with the latest updates from Patch.

Option #2 Total Project Costs: $163,850,000

However; Webb & Associates November 2, 2016, Workshop did not include Recycled Water and listed the following Cost Estimates:

Find out what's happening in Banning-Beaumontfor free with the latest updates from Patch.

Option #1 Total Project Costs: $95,744,000

Option #2 Total Project Costs: $163,919,000

Last heard; Project Cost is pushing $110 Million.

It’s a little hard to believe that Knoll made an ‘honest mistake’ when the source of the Sewer Feasibility Study is himself.

Webb & Associates’ Feasibility Study also didn’t include the cost to replace the clay sewer pipes that were installed in the original parts of Beaumont in 1929.

The views expressed in this post are the author's own. Want to post on Patch?