Traffic & Transit

San Juan Creek Channel Repairs Bring Trail Closures Near Stonehill Drive

Work is scheduled through Thursday, Dec. 31, with weekday construction noise and intermittent trail closures near the channel.

Trail users near the San Juan Creek Channel at Stonehill Drive may encounter intermittent closures during OC Public Works repairs. Construction is scheduled from Wednesday, Nov. 4, through Thursday, Dec. 31, 2026.

Crews will remove and replace approximately 225 linear feet of damaged concrete channel lining. The work is intended to maintain the channel and support flood protection for the surrounding community.

Working hours are 7 a.m. to 5 p.m. Monday through Friday, and adjacent residents and property owners should expect temporary construction noise. Signs and flag personnel will divert traffic during closures. The schedule is tentative and subject to change because of weather and other factors.

Find out what's happening in Huntington Beachfor free with the latest updates from Patch.

Public access to flood control channels is prohibited, and people should stay clear of the project area and follow posted signs and personnel directions. For project questions, contact supervising construction inspector Malachi Rios at 714-448-1672 or senior construction inspector Mike Alfaro at 714-448-0804. Inquiries can also be emailed to projectinfo@pw.oc.gov.

Source: β€œMaintenance Alert: San Juan Creek Channel Repair at Stonehill Drive” (pw.oc.gov)

Find out what's happening in Huntington Beachfor free with the latest updates from Patch.

Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

Found a problem with this article? Let us know.