Long Beach Approves Nearly $34M In Contracts For Pacific Avenue Overhaul
Two projects will reshape 3.6 miles of Pacific Avenue with protected bike lanes, safer crossings and major transit upgrades.

LONG BEACH, CA — A sweeping overhaul of Pacific Avenue is moving forward after the Long Beach City Council approved nearly $34 million in construction contracts to transform 3.6 miles of roadway, bringing protected bicycle lanes, safer pedestrian crossings and major transit improvements to one of the city's most dangerous corridors.
The council approved both contracts Nov. 10 on separate 7-0 votes, with Councilmembers Cindy Allen and Roberto Uranga absent. The projects will cover Pacific Avenue from Ocean Boulevard to Wardlow Road, with construction anticipated to begin in January 2027.
The investment targets a troubling safety record. According to city presentations, Pacific Avenue recorded nine fatal collisions and 75 pedestrian and bicycle crashes between 2018 and 2022. The city's 2020 Vision Zero Action Plan identified the southern section as part of its fourth most dangerous corridor for pedestrians and bicyclists.
Find out what's happening in Long Beachfor free with the latest updates from Patch.
Protected Bike Lanes And Safer Crossings
The southern project will transform approximately 1.6 miles of Pacific Avenue between Ocean Boulevard and Pacific Coast Highway. All American Asphalt of Corona received a $12.17 million construction contract, with a 15% contingency bringing the maximum authorized amount to $14 million.
Improvements include physically separated bicycle lanes, reconstructed sidewalks, accessible curb ramps, upgraded traffic signals and rehabilitated pavement. The project will also introduce new bus stop amenities, improved pedestrian crossings and traffic signal upgrades at 10th and 15th streets. Near Washington Middle School, plans call for a raised bus boarding island to improve accessibility.
Find out what's happening in Long Beachfor free with the latest updates from Patch.
The roadway will be reconfigured to reduce vehicle speeds and improve safety for cyclists and pedestrians, while maintaining access for motorists and transit riders. The city's estimated overall cost for the southern project is $23.41 million, including engineering, design, construction oversight and related expenses. The council also authorized $20.74 million in grant-backed budget appropriations for the construction phase.
Improvements Extend North To Wardlow Road
A separate, approximately two-mile project will continue the improvements north from Pacific Coast Highway to Wardlow Road. Sully-Miller Contracting Company of Brea received a $17.12 million contract, with a 15% contingency increasing the maximum authorized amount to $19.68 million.
According to the city's project information, the work includes six new signalized intersections, 13 bus shelters, 33 ADA-compliant curb ramps and 12 curb extensions designed to shorten pedestrian crossings.
Plans also call for pavement rehabilitation, improved crosswalks and bicycle infrastructure, including painted bike lanes between Pacific Coast Highway and 31st Street and a protected, two-way bikeway between 31st Street and Wardlow Road. The northern project's estimated overall cost is $29.33 million, supported primarily by a $25 million federal Safe Streets for All grant and local transportation funding.
Construction Ahead Of 2028 Olympics
Together, the projects carry estimated total costs of $52.74 million, although the construction contracts approved Nov. 10 have a combined maximum value of $33,685,343. The larger figure includes planning, engineering, construction management and other expenses beyond the construction contracts themselves.
Both projects form part of Long Beach's Elevate '28 infrastructure initiative, intended to improve transportation and public facilities ahead of the 2028 Olympic and Paralympic Games. City presentations anticipate construction beginning in January 2027 and finishing in early 2028, although the northern project's staff report identifies fall 2027 as its targeted completion date.
City officials also plan to coordinate construction with Metro, transit operators, utilities and nearby developments. The improvements are intended to create a safer, more accessible Pacific Avenue, connecting downtown with neighborhoods farther north while addressing longstanding concerns about speeding, dangerous crossings and gaps in the bicycle network.