Metro Unveils Plan To Complete 32-Mile Riverside Path Through LA County

The $872 million project would close an eight-mile gap in the bike path, but Metro still needs funding to complete the entire route.

An eight-mile gap separates two exiting segments of the LA River Path, including this section that runs through Elysian Valley/Frogtown. (Chris Lindahl/Patch)

LOS ANGELES, CA — Metro is recommending an $872 million plan to close the last major gap in the Los Angeles River bike path, a project that would eventually allow cyclists and pedestrians to travel along a continuous riverside route from the San Fernando Valley to Long Beach.

The proposed route would connect existing trails between Elysian Valley and Vernon, creating a continuous path through downtown Los Angeles and communities including Boyle Heights and Maywood.

Subscribe

Under the proposal, known as Modified Option 2, Metro would initially build two sections totaling 5.5 miles while seeking additional funding to complete the remaining stretch.

The first section would run from Riverside Drive to Broadway/Spring Street, while the second would extend from Sixth Street to Atlantic Boulevard. Metro staff recommends constructing both sections simultaneously.

Combined with existing and planned bike lanes near the river, the two sections would provide a protected route for cyclists across the entire eight-mile gap until the remaining 2.5-mile section between Broadway/Spring Street and Sixth Street can be built, according to Metro.

The Metro Board of Directors is scheduled to consider the recommended route on Dec. 3, following reviews by two board committees on Nov. 18 and 19.

The project currently has $433 million in funding from Measure M, the transportation sales tax approved by Los Angeles County voters in 2016. With construction estimated at $872 million, Metro faces a funding gap of approximately $439 million.

The recommended design would place much of the path along the top of the riverbank or within the side of the embankment, with elevated sections where necessary to cross railroad tracks and other obstacles.

Metro officials said the design would reduce construction costs and complications associated with the numerous bridges, power lines, railroad tracks and other infrastructure along the river.

The proposed route would also include three new river crossings and 10 access points, including seven on the east bank and three on the west bank. Additional access points at Seventh Street and near Bandini Boulevard and Soto Street could be added if funding becomes available.

The recommendation follows Metro's release of a draft environmental impact report in December 2025 that evaluated seven possible alternatives.

Earlier plans considered placing the bicycle path along the bottom of the concrete river channel, but Metro rejected that approach because of safety and accessibility concerns.

A path at the bottom of the channel could require extended closures during storms and would present challenges involving flood control, emergency access and connections to surrounding streets, according to Metro.

Officials also cited concerns about visibility and the need for longer, steeper ramps to reach a path located at least 25 feet below street level.

The project has faced delays as its scope and cost have increased.

Metro previously anticipated completing the eight-mile stretch in 2027, ahead of the 2028 Olympic and Paralympic Games, but pushed back that timeline as engineering and environmental reviews continued.

Another unresolved issue is determining which public agencies will build, operate and maintain the completed path.

Metro owns less than 1% of the land required for the project and does not intend to operate or maintain the trail once it opens.

The Los Angeles County Flood Control District is expected to lead a governance study examining how the path and the broader 51-mile Los Angeles River trail network would be managed.

Metro will fund the study and work with the county to establish its scope, schedule and budget.

Once agencies agree to take responsibility for the path, Metro plans to advance the project's environmental review and continue design and permitting work.

Officials have not announced a construction start date or a revised completion timeline for the entire eight-mile extension.

The project is intended to improve walking and biking connections between neighborhoods, transit stations and employment centers along the river, particularly in communities that have historically had limited access to protected bicycle infrastructure.

The public can review project documents, maps and environmental studies at Metro's LA River Path website.

Information about the Dec. 3 board meeting, including options to attend in person or watch online, is available through Metro's board meeting website.

City News Service contributed to this report.

More from Los Angeles
News | 2h
News | 1h
News | 3h
See more on Patch >

Sign up for free local newsletters and alerts for the
Los Angeles Patch

Patch.com is the nationwide leader in hyperlocal news.
Visit Patch.com to find your town today.

©2026 Patch Media. All Rights Reserved

Do Not Sell My Personal Information