The interior of the building is changing rapidly with the installation of sheetrock on the first floor. Second floor framing is nearing completion, and work on the roof deck will start after the holiday. Last week's rain had little impact on the work as plastic sheeting covered the roof. Project is still on budget and is slated for completion this fall. More info: http://www.cityofnovato.org/Index.aspx?page=1534