Palos Verdes Drive South Traffic Restrictions Continue Through Wednesday

The traffic restrictions are part of a project to repair 7,500 feet of aging sewer pipe, with work continuing into early 2027.

A map from the Los Angeles County Sanitation Districts shows the sewer repair route (green) and temporary bypass line (red) near Palos Verdes Drive South. (Los Angeles County Sanitation Districts/Google Earth)

RANCHO PALOS VERDES, CA — Motorists traveling along Palos Verdes Drive South should expect delays through Wednesday, Oct. 14, as crews continue work on a major sewer rehabilitation project involving nearly 1.5 miles of aging underground infrastructure.

According to an advisory issued Monday by the City of Rancho Palos Verdes, traffic restrictions are in effect along the oceanside lane between Seacliff Drive and Palos Verdes Drive East.

Subscribe

Traffic control is scheduled from approximately 8:30 a.m. to 6 p.m. through Wednesday, with motorists advised to allow additional travel time or consider alternate routes.

The restrictions are associated with the Los Angeles County Sanitation Districts' Rancho Palos Verdes Trunk Sewer Repair Project, which involves rehabilitating approximately 7,500 feet of sewer pipe that has deteriorated over 60 to 70 years of service.

Rather than excavating and replacing the entire pipeline, crews are installing a lining system inside the existing sewer, a method the agency says is quicker and less disruptive than constructing a new line. Associated manholes will also be repaired.

Construction is taking place near Shoreline Park and Trump National Golf Course, with temporary above-ground sewer bypass infrastructure extending along Palos Verdes Drive South from north of Schooner Drive to Shoreline Park.

According to the Sanitation Districts, portions of the eastbound, oceanside lane will be closed intermittently during construction, with flaggers directing vehicles into the westbound lane.

The broader project began in September and is scheduled to continue through February 2027. Regular construction hours are 8:30 a.m. to 6 p.m. Monday through Friday and 8 a.m. to 6 p.m. Saturdays.

Residents with questions can contact Sanitation Districts resident engineer Jennifer James at 310-892-0842 or jjames@lacsd.org. After-hours problems and odor concerns can be reported to the agency's 24-hour hotline at 562-437-6520.

More from Palos Verdes
News | 4d
News | Oct 2
News | Sep 30
See more on Patch >

Sign up for free local newsletters and alerts for the
Palos Verdes Patch

Patch.com is the nationwide leader in hyperlocal news.
Visit Patch.com to find your town today.

©2026 Patch Media. All Rights Reserved

Do Not Sell My Personal Information