Palos Verdes School Turf Plan Draws 6 Bids Amid Parent Opposition
Construction bids range from $1.6 million to $2.88 million as the district continues to review health and environmental concerns.
PALOS VERDES ESTATES, CA — A proposal to replace a natural grass athletic field with artificial turf at Palos Verdes Intermediate School has drawn six construction bids, but questions over the project's cost, environmental impact and student safety remain unresolved as school district officials prepare to bring the issue back before the Board of Education in December.
The Palos Verdes Peninsula Unified School District received construction bids ranging from approximately $1.6 million to $2.88 million on Nov. 18, Assistant Superintendent of Administrative Services Brenna Terrones told Patch Monday. The district has yet to decide whether to proceed with the project, which has faced organized opposition from parents since September.
The apparent low bid came in at approximately $1.597 million, rising to $1.757 million with a required contingency. Those figures do not include the additional cost of the artificial turf option.
Find out what's happening in Palos Verdesfor free with the latest updates from Patch.
"The District is continuing to evaluate the bids, turf options, costs, operational needs, available funding, and community feedback before determining next steps," Terrones said.
Questions Remain Over Funding
Find out what's happening in Palos Verdesfor free with the latest updates from Patch.
Although the construction bids came in below an earlier $3.1 million project estimate, the project's total cost remains undetermined. The district issued separate solicitations for construction work and synthetic turf, both of which had Nov. 18 submission deadlines.
Approximately $2 million in restricted developer-fee funding has been identified for the project, Terrones said, and the district is assessing the updated construction and turf pricing against available resources. No additional funding has been committed. Terrones also stressed that the proposed installation is separate from the district's Measure SOS school facilities bond program.
"No Measure SOS bond funds can or will be used to fund this project," she said.
Parents Rally Behind 'Roots Not Rubber'
Opposition to the proposed installation gained momentum in the days leading up to the Sept. 23 Board of Education meeting, when parents began circulating a petition challenging the replacement of the school's natural grass field.
Among those voicing concerns are parents Beth and Adam Wagner, who have called for a more comprehensive assessment of the project's potential environmental, financial and health consequences before the district commits to construction.
The petition had gathered more than 300 signatures by Nov. 10, and opponents had adopted the slogan "Roots Not Rubber," according to the Daily Breeze.
Parents have raised concerns about elevated playing surface temperatures, potential microplastic pollution and the eventual cost of replacing synthetic turf. Given the Peninsula's coastal setting, they have also questioned whether synthetic materials could enter local waterways and ultimately reach the Pacific Ocean through stormwater runoff.
At its Sept. 23 meeting, the Board of Education voted 4-1 to solicit bids while directing staff to further examine the project's environmental, financial and safety implications. Board President Sara Deen cast the dissenting vote. The authorization allowed the district to obtain updated pricing without committing it to construction.
Weighing The Benefits And Risks
The proposal dates to 2022, when a district advisory committee identified athletic field improvements as a priority. Synthetic turf projects were subsequently developed for both Palos Verdes Intermediate and Ridgecrest Intermediate schools, but only the Ridgecrest installation proceeded at the time because of funding constraints and competing district priorities, according to the Daily Breeze.
Among the operational considerations is the demand placed on district athletic fields, which accommodate school programs as well as community and youth sports organizations outside school hours. While synthetic turf can reduce irrigation needs and accommodate more intensive use, the district is also examining questions surrounding surface temperatures, environmental impacts, maintenance and long-term replacement costs.
Terrones confirmed that the district's environmental, health and safety review remains ongoing, with staff examining peer-reviewed research and other credible sources as part of its assessment.
"Each option presents benefits, limitations, and tradeoffs that should be considered based on available research, operational needs, and community input," Terrones said. "We recognize that there are differing perspectives within the community and that no single solution will satisfy every stakeholder."
The district anticipates presenting the procurement results to the Board of Education on Dec. 9, providing another opportunity for public discussion before any final decision is made. Meeting information and agendas are available on the district's board calendar.