The city has installed 1,300 feet of flood barriers and removed a public dock as potentially record-breaking king tides approach.

Contractors from Connolly Pacific conduct breakwater repair work Sept. 17, 2026 in Redondo Beach, California for the U.S. Army Corps of Engineers' Redondo Beach-King Harbor breakwater repair project.
Contractors from Connolly Pacific conduct breakwater repair work Sept. 17, 2026 in Redondo Beach, California for the U.S. Army Corps of Engineers' Redondo Beach-King Harbor breakwater repair project. (U.S. Army Corps of Engineers photo by Shawn Davis, Los Angeles District Public Affairs)

REDONDO BEACH, CA — Nearly a month after seawater inundated businesses along Redondo Beach's International Boardwalk, the city has installed 1,300 feet of portable flood barriers and removed a public floating dock elsewhere in King Harbor as part of preparations for potentially damaging winter conditions.

The new flood defenses arrived at 3 a.m. Monday and were installed later that day by the city's Public Works Department, according to a Facebook post by Mayor Jim Light. Their effectiveness could be tested within days, with some of the highest tides of the year expected over Thanksgiving.

"We will see how they perform with the King Tides this week that are supposed to peak on Wednesday," Light wrote.

Find out what's happening in Redondo Beachfor free with the latest updates from Patch.

The installation comes as Los Angeles County officials warned Tuesday that potentially record-breaking king tides, dangerous surf and rip currents could threaten coastal communities, identifying the coastline between Santa Monica and Palos Verdes as one of the areas of greatest concern.

Nearly $100,000 In Flood Protection

The purchase of the barriers follows October's exceptionally high tides, when seawater reached the entrances of several International Boardwalk businesses and penetrated some establishments despite the deployment of sandbags.

Find out what's happening in Redondo Beachfor free with the latest updates from Patch.

An administrative report prepared by Public Works Director Andrew Winje for the Nov. 3 City Council meeting recommended spending up to $100,000 on a portable flood protection system designed to encircle Basin 3, including the International Boardwalk.

Supplied by Garrison Systems LLC, the modular Mayim Barrier system measures 30 inches high and was estimated to cost $92,543.35. The proposed purchase was subject to satisfactory testing and evaluation, with city officials seeking to secure delivery before the next round of exceptionally high tides. Light subsequently confirmed that the council had approved the purchase. The final cost has not been disclosed.

As Patch reported Oct. 27, Project Barley Taps and Grill suffered flooding that ruined its flooring, underscoring the vulnerability of waterfront businesses to unusually high water levels. While the portable barriers are intended to provide short-term protection, their installation comes amid broader concerns about the condition of the waterfront's aging flood defenses.

"Hats off to Public Works who worked to get the barriers installed quickly!" Light wrote.

Floating Dock Removed For Winter

Across King Harbor, preparations for the winter have extended beyond protecting businesses from rising seawater to safeguarding infrastructure that could be damaged by elevated water levels and rough conditions. The public floating hand-launch dock behind Seaside Lagoon has been removed as a precaution against anticipated El Niño conditions and is expected to be reinstalled in March 2027, the Easy Reader reported Monday.

The removal was previously discussed at the Nov. 9 Harbor Commission meeting, when city staff outlined plans to protect the facility over the winter while maintaining alternative launching options for boaters. The nearby boat hoist will remain operational throughout the winter. Although the free public hand-launch facility ordinarily operates from April through October, physically removing the dock is intended to protect it from potentially damaging winter conditions.

More Exceptionally High Tides Ahead

The coastal flooding that affected Redondo Beach in October was part of a much wider phenomenon that saw water levels reach unprecedented heights at several California monitoring stations. According to a Nov. 4 report from the National Oceanic and Atmospheric Administration, tide gauges in Los Angeles, Santa Barbara, San Diego and La Jolla registered their highest observed water levels on record in late October, while Santa Monica recorded its second-highest.

Exceptionally high astronomical tides coincided with an ongoing marine heatwave and El Niño-driven Kelvin waves, which carry warm water eastward across the Pacific Ocean and can temporarily elevate sea levels along the West Coast. As of Tuesday afternoon, the National Weather Service had a coastal flood advisory in effect for Los Angeles County beaches through 6 a.m. Thursday, followed by a coastal flood watch Thursday morning.

Breaking waves of 6 to 11 feet are forecast Wednesday and Thursday, bringing the potential for dangerous rip currents, substantial beach erosion and damage to docks and other vulnerable coastal infrastructure. County officials are urging residents and visitors to avoid jetties, rocks and piers during hazardous surf conditions and be prepared to move to higher ground if flooding occurs.

Regardless of how Redondo Beach's new flood defenses perform over Thanksgiving, another significant test could come just before Christmas, with NOAA identifying Dec. 22-26 as another period of elevated coastal flooding risk.