SAN MATEO COUNTY, CA — New data center development has been temporarily banned in unincorporated San Mateo County as officials weigh how to regulate the facilities amid growing concerns about their environmental impact.
The San Mateo County Board of Supervisors unanimously approved a 45-day moratorium Tuesday, immediately halting data center development in areas outside incorporated cities while county staff evaluate potential regulations.
The temporary ban was adopted as an urgency ordinance, meaning it took effect immediately.
Data centers house computer equipment used to store, manage and process large amounts of information.
However, they also require substantial amounts of electricity and water, raising concerns about their environmental impact as demand for AI infrastructure grows.
Despite increasing opposition to data center development in parts of the Bay Area, technology companies continue to pursue new facilities.
San Mateo County staff are already studying whether data centers should be permitted in unincorporated areas and, if so, under what conditions.
The moratorium gives officials additional time to consider potential regulations before allowing new projects to move forward.
Before the initial 45-day period expires, supervisors can vote to extend the ban for up to one year. The board would then have the option of approving another extension for an additional year.
The ordinance applies only to unincorporated San Mateo County and does not establish a countywide ban within incorporated cities.
County officials have not yet announced what permanent regulations, if any, they may adopt once the review is complete.