The San Rafael City Council approved a $3.4 million redesign of the Second and Fourth streets intersection on Monday, Oct. 19. The West End project will shorten crossings, improve accessibility and complete a separated bicycle connection.
Construction is expected to begin in winter 2026/spring 2027 and take approximately four months to be functionally complete. A $3 million federal grant through the One Bay Area Grant Program will cover most costs, with $400,000 coming from the city's Gas Tax Fund.
The Fourth Street corridor, known as the Miracle Mile, carries nearly 40,000 vehicles daily and connects San Rafael with San Anselmo and West Marin. Its outdated signals and pedestrian facilities that do not meet current accessibility standards are among the problems the project addresses.
The redesign will reduce the intersection from five road connections to three, with shorter crossings and accessible pedestrian facilities. It will also complete a separated bikeway from Shaver Street to West End Avenue, connecting to the Greenfield Avenue bicycle route.
The north-south pedestrian crossing will move to the intersection's east side, and the westbound Second Street left-turn lane toward Marquard Avenue will be removed. A business-access-only lane with its own signal will be added on the north side, along with new traffic signals, lighting and a transit stop.
Construction planning includes coordination with other expected city and utility projects in the area. Residents can check the project webpage for schedules, work-area maps and expected detours, delays and lane closures, or sign up for email updates.