Rep. David Scribner Alerts Residents of I-84 Construction
Travelers can expect delays beginning tonight at 7pm and ending tomorrow morning around 6am.
Rep. David Scribner would like to alert you to construction on I-84 tonight that may impact your travel plans. The state DOT announced they will be performing bridge maintenance and rehabilitation of highway bridges which carry 1-84 over Center Street in Newtown.
The planned work necessitates traffic shifts which could create slowdowns or delays. Please use caution when driving in the area or find an alternate route.
Construction is scheduled to take place beginning at 7 p.m. Wednesday night, October 29, 2014. The new alignment will be in place for commuter traffic by 6 a.m. Thursday morning, October 30.
Find out what's happening in Brookfieldfor free with the latest updates from Patch.
The full DOT release is included below.
Traffic Shift Scheduled as work continues on the bridge carrying Interstate 84 Westbound over Center Street in Newtown
Find out what's happening in Brookfieldfor free with the latest updates from Patch.
The Connecticut Department of Transportation is announcing that traffic will be shifted on Interstate 84 to rehabilitate Bridge No. 04256 over Center Street in Newtown. The traffic shift on Interstate 84 WB is scheduled for Wednesday night, October 29, 2014.
The work for the traffic shift includes relocation of temporary precast barrier, removal of current pavement markings, installation of new pavement markings, and necessary signing modifications.
The project involves the rehabilitation of Bridge Nos. 04255 and 04256 which carry 1-84 over Center Street, a local road in the town of Newtown. The structures are single-span multi-beam-type structures. Bridge No. 04255, built in 1978, carries two lanes of Interstate 84 eastbound traffic. Bridge No. 04256, built in 1977, carries two lanes of westbound traffic. The two bridges are parallel structures, set approximately 90 feet apart and are situated 0.17 miles west of the Housatonic River.
The traffic shift will occur in the westbound direction of I-84 with work beginning at 7 p.m. Wednesday night, October 29, 2014. The new alignment will be in place for commuter traffic by 6 a.m. Thursday morning, October 30. The rain date for this shift is Thursday night, October 30th to Friday morning, October 31, 2014.
DOT Project No. 0096-0194/195 was awarded to Manafort Brothers, Inc. at a cost of $5,919,944.30 on August 17, 2012 and is scheduled to be completed in April 2015.