Darien's Annual Road Paving Projects Start Wednesday: Find Out Where
Motorists should drive with caution and be on the lookout for crews. Minor traffic delays could occur.

DARIEN, CT — A total of 21 roads in Darien are scheduled to be repaved this summer, beginning this week, the town's Department of Public Works announced.
The project is slated to begin on Aug. 9 and run through Aug. 25, weather permitting. Motorists are warned to use caution if driving through the areas, but avoid those roads if possible while the work is underway. Minor traffic delays are likely.
Emergency access will be available at all times, and police officers will be on-hand to direct traffic and assist residents during the project.
Find out what's happening in Darienfor free with the latest updates from Patch.
"Preparatory work will precede paving on all of the above roads," wrote officials in a statement. "Dates listed include milling and paving. Road surfaces will have raised structures during these dates."
Driveway access will be limited during paving operations. "However, no single driveway should be closed
for more than an hour. On street parking will be suspended during paving operations."
Find out what's happening in Darienfor free with the latest updates from Patch.
Contact the Department of Public Works at 203-656-7346 for further information. Below are the roads to be repaved and the dates for the work:
- Stony Brook Road South: Stony Brook Road to Cul De Sac - August 9 to August 16
- Stony Brook Road: West Avenue to Leroy Avenue - August 9 to August 16
- Center Street # 1: Boston Post Road to Old Kings Hwy S. - August 10 August 16
- Center Street # 2: Center Street to Old Kings Hwy S. - August 10 to August 16
- East Lane: Old Kings Hwy N. to Cul de Sac - August 11 to August 17
- Point O’Woods Road South: Point O’Woods Road to Cul de Sac - August 11 to August 17
- Point O’Woods Road: Birch Road to Richmond Drive - August 11 to August 17
- Woods End Road: Sylvan Road to Cul de Sac - August 14 to August 18
- Dorchester Road: Stephen Mather Road to Brookside Road - August 14 to August 21
- Tower Drive: Mansfield Avenue to Cul de Sac - August 15 to August 21
- Woodway Road: Hoyt Street to Stamford City Limits - August 16 to August 21
- Abbey Road: Intervale Road to 9 Abbey Road - August 16 to August 22
- Stanley Road: Intervale Road to Middlesex Road - August 16 to August 22
- Devon Road: Stanley Road to Chester Road - August 17 to August 22
- Chester Road: Middlesex Road to End of Chester Road - August 18 to August 23
- Intervale Road: Holmes Avenue to 38 Intervale Road - August 18 to August 23
- Holmes Avenue: West Avenue to 127 Holmes Avenue - August 18 to August 23
- Holmes Avenue: Holmes Court to Middlesex Road - August 18 to August 24
- Robinson Street: West Avenue to Belleval Street - August 21 to August 24
- Brown Street: West Avenue to Belleval Street - August 21 to August 24
- West Avenue: Stamford City Limits to 348 West Avenue - August 21 to August 25