Here's The February Construction Update For Central Middle School
Take a look back at work that was completed in January and see what's ahead for February at the Central Middle School construction site.
GREENWICH, CT — Greenwich Public Schools last week issued its February update on construction at the new Central Middle School.
The new 125,000 gross square-foot building is being constructed just north of the current school.
The existing school will continue to function until the new structure is complete and receives a final certificate of occupancy.
Find out what's happening in Greenwichfor free with the latest updates from Patch.
If all goes according to plan, the new $112 million CMS could open before the start of the 2026-2027 school year.
Here's work that was completed in January:
Find out what's happening in Greenwichfor free with the latest updates from Patch.
- Continued exterior wall façade installations throughout.
- Substantially completed interior framing and in-wall rough-ins throughout the building.
- Began painting second-floor classroom spaces.
- Began ceiling installations in classroom spaces.
- Continued work in the utility corridor.
- Continued exterior storm infrastructure work.
- Continued drywall and taping on the first floor.
- Continued high-ceiling auditorium fit-out.


Here's a look at work expected to take place in January:
- Continue drywall and taping on the first floor.
- Begin painting and ceiling installations on the first floor.
- Begin flooring and finishes in second-floor classroom spaces.
- Continue exterior wall façade installation throughout
- Continue utility corridor and underground utility infrastructure work.
- Continue auditorium and gym fit-out.
The project has received temporary exemptions to the town’s noise ordinance, permitting Saturday morning work. These exemptions are submitted monthly when needed.