GREENWICH, CT — The Central Middle School Building Committee recently shared its second project update as construction on the new CMS continues.
The new 125,000 gross square-foot building is being constructed just north of the current school.
The existing school will continue to function until the new structure is complete and receives a final certificate of occupancy.
Find out what's happening in Greenwichfor free with the latest updates from Patch.
If all goes according to plan, the new $112 million CMS could open before the start of the 2026-2027 school year.
Read also:
Find out what's happening in Greenwichfor free with the latest updates from Patch.
- May Update On Central Middle School Project
- May 2025 'Difference Makers' Announced In Greenwich Public Schools
- Officials Break Ground On New $112 Million Central Middle School
According to the latest Central Middle School Campus Connections update, the following work was completed in May:
- The truck route is Stanwich Road to Orchard Road, avoiding school drop-off and dismissal times (Monday – Friday) and continues to perform well
- Continuation of footing and foundation systems for the building
- Start backfill and waterproofing operations within the building footprint
- Begin footing drain installation
- Ongoing processing operations of soils
Here is work anticipated to take place in June:
- Continue installing footing and foundations systems for building structure
- Situate the underground utilities
- Continuing backfill operations
- Start erecting the steel structure of the school building
- Begin masonry for gym walls
- Construction work will also take place on Saturdays this month