A large crane that was to have lowered two pedestrian bridges into place Wednesday had to be inspected for safety after it was discovered to have been vandalized the night before.
A massive crane was supposed to lower a pair of pedestrian bridges into place over Birch Mountain Brook early Wednesday, advancing the latest leg of the Charter Oak Greenway that much closer to completion, which Public Works Director Mark Carlino insisted would make for the perfect photo opportunity for the local media.
Except when the crew showed up to begin work at about 6:30 a.m. Wednesday morning they discovered that vandals had smashed the windows of the crane and sprayed a fire extinguisher all over the inside of the cab sometime during the night.
So, instead of that photo op, the police were called in to investigate and the crane had to be inspected for safety before it could be operated, delaying the installation of the bridges by several hours.
Find out what's happening in Manchesterfor free with the latest updates from Patch.
“They just broke windows, no graffiti,” said David Slossar, a construction engineer for the town. “That’s weird.”
Carlino said inspectors cleared the crane and the bridge installation began around 11:30 a.m., and that the crew from Marino Crane, a Middletown company that operated the crane, was paid a flat fee and not by the hour, so the delay came at no extra cost to the town.
Find out what's happening in Manchesterfor free with the latest updates from Patch.
“These are all just things that are ancillary to getting the job done,” Carlino said.
The first of the two bridges, 75-feet long and 12-feet wide, was then lowered into place from the Gardner Street bridge over I-384 and was set by 12:30 p.m.; a second 70-foot bridge was lowered into place further along the trail by the crane later that afternoon.
The latest leg of the Charter Oak Greenway, which will extend the bike and pedestrian trail an additional 0.7 miles, is on pace to be finished by the end of August, Carlino said.
The project cost about $750,000, according to Carlino, with federal funds covering the bulk of the costs.
The Manchester portion of the Charter Oak Greenway, currently a 3.3-mile trail, begins at the East Hartford town line and extends to Charter Oak Park. The trail also ties into the larger East Coast Greenway, which is planned to someday extend 2,600 miles from Florida to Maine.