From Ferreira Construction: Four crews from Ferreira Construction will continue construction activities to install and improve our natural gas distribution system in New Canaan:
• Gas Main Installation:
o Crew 1 will be installing gas main on Main Street between Harrison Avenue and Maple Street during the hours of 7 a.m. – 5 p.m., Monday through Friday.
o Crew 2 will be installing gas main on Harrison Avenue during the hours of 7 a.m. – 5 p.m., Monday through Friday.
o The hours for in-street construction activities may vary, depending on location and weather.
o Temporary paving activities will be performed in conjunction with our construction activities as needed.
o There will be no construction work performed on Saturday and Sunday.
o Traffic flow will be maintained where possible, however, drivers may experience delays due to alternating one-way traffic, as well as, occasional lane closures.
• Gas Service Installation:
o Crew 3 will be installing gas services on Brooks Avenue and Farm Road during the hours of 7 a.m. - 5 p.m., Monday through Friday.
o Crew 4 will be installing gas services on Mortimer Street and Brinckenhoff Avenue during the hours of 7 a.m. - 5 p.m., Monday through Friday.
o Our construction activities include individual service line installations and we will be working directly with specific homeowners and providing appointments to complete our work.
o The hours for in-street construction activities may vary, depending on location and weather.
o Temporary paving activities will be performed in conjunction with our construction activities as needed.
o There will be no construction work performed on Saturday and Sunday.
o Traffic flow will be maintained where possible, however, drivers may experience delays due to alternating one-way traffic, as well as, occasional lane closures.
What You Can Expect:
• The hours for in-street construction work may vary, depending on location, and the construction crews will be working daytime hours.
• Access will be maintained to residences and businesses, as well as ensure priority passage of emergency vehicle traffic through construction areas.
• Construction activities may take place at multiple sites along the route until the project is completed.
• Work zones will be protected from pedestrians and vehicles.
• Police officers or flagmen will oversee traffic control.
• Please note that construction work is weather dependent, and all construction activities are subject to change without notice.
Find out what's happening in New Canaanfor free with the latest updates from Patch.
Additional Information:
Eversource remains committed to providing reliable service as well as accurate and timely information. Keeping the lines of communication open is an important part of our work in your community.