Schools

Ridgefield Schools Weigh Closing Branchville, Rebuilding Veterans Park Amid Mounting Budget Pressures

Ridgefield school officials review a proposed elementary school consolidation, rising special education costs and capital spending needs.

RIDGEFIELD, CT β€” Ridgefield could replace Veterans Park Elementary School with a larger building, close Branchville Elementary School and redraw elementary school attendance boundaries under a long-term facilities master plan presented to the Board of Education on Nov. 23.

The recommendations, developed by consultants MP Planning Group and StudioJAED, come as the district confronts $197.5 million in identified facility needs, a growing special education budget deficit and pressure from the Board of Finance to limit spending increases.

No school closures or construction projects were authorized at the meeting.

Find out what's happening in Ridgefieldfor free with the latest updates from Patch.

Board Chair Tina Malhotra warned that the upcoming budget season would require difficult decisions about spending and educational programming.

"Asking a hard question is not an attack, it is not disloyalty to anyone," Malhotra said. "We will debate these issues, not the person."

Find out what's happening in Ridgefieldfor free with the latest updates from Patch.

Consultants Recommend 'Newer And Fewer' Schools

Patrick Gallagher, a principal with MP Planning Group, presented a long-term strategy that would reduce the district's elementary schools from six to five while increasing available classroom space.

The proposal calls for constructing an approximately 75,000-square-foot Veterans Park Elementary School with four classrooms per grade and a five-classroom preschool center. Preliminary construction costs are estimated at $90 million to $100 million.

Related: Ridgefield Finance Board Sets Budget Targets As Schools Face Potential Deficit

The existing Veterans Park building would remain operational during construction. Once students moved into the new school, the original building would be demolished to accommodate other site needs, potentially including parking and bus circulation.

Branchville Elementary School would close following completion of the project, and its students would be reassigned through districtwide elementary school redistricting.

Consultants identified Branchville as having the highest facility improvement needs per square foot among the district's schools.

Replacing Veterans Park and closing Branchville could avoid approximately $28 million in improvements to the two existing buildings, Gallagher said.

However, consultants cautioned that Ridgefield does not currently have sufficient classroom capacity to close an elementary school without adding space elsewhere.

"We can't simply close a building today and reallocate the students," Gallagher said.

The proposed consolidation would leave elementary schools operating at a projected peak utilization rate of approximately 96 percent.

Short-Term Plan Would Preserve All Schools

Consultants recommended a separate, shorter-term strategy that would maintain all existing schools while prioritizing essential infrastructure improvements.

The plan calls for reclaiming space occupied by Cadence Academy at Barlow Mountain Elementary School to establish an eight-classroom districtwide preschool center.

Moving preschool programming into that space would free classrooms at Barlow Mountain and Veterans Park for elementary instruction, reducing projected peak elementary school utilization to approximately 92 percent.

Phil Conte, president and CEO of StudioJAED, said essential improvements include heating, ventilation and air conditioning systems, roofs, windows, electrical infrastructure and deteriorating exterior surfaces.

The consultants identified five schools where capital improvements could proceed regardless of the district's eventual consolidation decision:

  • Barlow Mountain Elementary School
  • Ridgebury Elementary School
  • East Ridge Middle School
  • Scotts Ridge Middle School
  • Ridgefield High School

The initial phase would require approximately $55 million in improvements.

Investments at Branchville, Farmingville, Scotland and Veterans Park elementary schools would be coordinated with decisions about the district's long-term configuration.

Gallagher cautioned against delaying those decisions for seven to 10 years, given the deteriorating condition of the buildings.

The consultants recommended establishing an implementation committee involving the Board of Education and other town governing bodies to evaluate financing, construction schedules and community support.

Board members requested additional financial analysis, including projected annual debt service, operating savings and the implications for taxpayers.

Enrollment Expected To Remain Stable

The updated demographic study projects that Ridgefield's overall kindergarten through 12th-grade enrollment will remain relatively stable over the next decade, ranging from 4,090 to 4,167 students.

Enrollment trends differ considerably among grade levels, however.

Elementary enrollment is projected to reach 1,878 students in the 2034-35 school year, while middle school enrollment is expected to decline by approximately 15 percent over the next five years before rebounding.

High school enrollment is expected to average approximately 1,415 students over the next five years before declining below 1,300 later in the projection period.

See Also: Ridgefield Finance Board Reviews $3.75M Battlefield Property Purchase, Delays Funding Decision

The study also anticipates that the enrollment imbalance between Ridgefield's two middle schools will narrow.

Scotts Ridge currently enrolls 104 more students than East Ridge, the largest difference recorded between the schools. By the 2031-32 school year, that gap is projected to decline to approximately 30 students.

Consultants cautioned that limited available classroom space makes elementary school redistricting difficult under the district's existing configuration.

Special Education Deficit Approaches $2 Million

Superintendent Susie Da Silva said the district's projected special education deficit, estimated at $1.8 million as of Oct. 31, had subsequently approached $2 million.

Christine Sipala, assistant superintendent of special services for Ridgefield Public Schools, outlined the factors contributing to the shortfall, including contracted services and costs associated with educating students outside the district.

More than 19 percent of Ridgefield's students have disabilities, according to Sipala's report.

She noted that the district must respond to individual student needs that can change after annual budgets have been developed and approved.

Board members requested a more detailed breakdown of the projected deficit, including the costs of out-of-district placements and contracted services, while maintaining student confidentiality.

The financial pressures extend into the district's planning for the 2027-28 fiscal year.

Preliminary estimates presented by Da Silva indicate that existing financial commitments alone would require a 5.39 percent increase in the overall operating budget. Those commitments include:

  • Compensation and related benefits, excluding medical insurance: 1.73 percentage points.
  • Medical benefits: 1.93 percentage points.
  • Special education: 1.48 percentage points.
  • Transportation: 0.25 percentage points.

Those estimates do not account for all potential increases in utilities, additional special education expenses or other operating costs.

The Board of Finance has recommended limiting the school district's operating budget increase to 3.35 percent.

Board members discussed potential efficiencies, staffing levels, class sizes, technology spending and the need to preserve student programming.

Board member Robert Martire urged the administration to identify what would be required to maintain educational performance and explain the consequences of reductions needed to meet a budget target.

Secretary Christine More expressed support for examining potential technology spending reductions, while board member Dawn-Marie Callahan urged the district to keep the needs of academically and intellectually gifted students in its longer-term planning.

Capital Spending Priorities Debated

The board also conducted its first formal review of the district's five-year capital improvement plan.

The administration's recommended annual capital spending plan of approximately $4.8 million is roughly twice the previous year's allocation of $2.4 million, which the Board of Finance has suggested maintaining.

An alternative spending scenario identified approximately $2.04 million in priority projects, with additional projects available for consideration depending on funding.

Board members discussed distinguishing critical health and safety improvements from projects that could be postponed, as well as the long-term consequences of deferring maintenance.

Related: Ridgefield School Board Debates Class Sizes, Capital Spending And Budget Pressures

Several members requested additional spending scenarios and clearer explanations of which projects would be delayed under a reduced capital budget.

High School Proposes Course For Future Teachers

Ridgefield High School administrators presented a proposed University of Connecticut Early College Experience course designed to introduce students to careers in education.

The semester-long course, "If You Love It, Teach It," would be available to juniors and seniors beginning in the 2027-28 school year.

Students would earn three UConn undergraduate credits and a half-credit toward high school graduation while studying teaching methods, child development and the foundations of American education.

The course would include a 10-hour classroom field experience.

According to the proposal, an existing family and consumer sciences teacher would teach the course without requiring additional staffing. Estimated costs total $2,424, including curriculum development, textbooks and teacher training.

The proposal is part of the district's effort to expand career-oriented educational opportunities and encourage students to consider entering the teaching profession.

Board Elects Officers, Hears Parent Concerns

The board unanimously reelected Malhotra as chair and elected Kathryn Graf as vice chair and More as secretary. The officers will serve one-year terms.

During public comment, resident Emily Fernandez raised concerns about student data privacy, parental notification of online accounts and the potential introduction of generative artificial intelligence on school-issued Chromebooks.

Dana Costabile, the parent of a Scotland Elementary School third grader, urged the board to reconsider its class-size guidelines, citing the demands placed on teachers responsible for classrooms approaching the district's 25-student limit.

The board also heard a request to reinstate AP Physics C at Ridgefield High School.

Board member Angela Rice reported that a Nov. 20 Teaching and Learning Committee meeting had been canceled after a Microsoft outage delayed the posting of its public notice. The committee hopes to reschedule the meeting.

The board approved its amended Nov. 9 meeting minutes and unanimously adopted its 2027 regular meeting schedule.

The district's facilities recommendations and proposed capital and operating budgets remain subject to further review.