Town of Ridgefield Milling And Paving Schedule For Aug. 5-12

Here's where you can expect to find delays next week…

RIDGEFIELD, CT — Here's the schedule of milling and paving on local roads Aug. 5-12, according to the Town of Ridgefield:

Monday, Aug. 5 Milling Begins:

  • Barlow Mountain Road from North Street to Route 116
  • Route 116 from Barlow Mountain Road to Craigmoor
  • Craigmoor Road (entire road)

Thursday, Aug. 8 Milling Begins:

  • Ligi’s Way
  • Farmingville Road

Monday, Aug. 12 Paving Begins:

  • Ligi’s Way
  • Farmingville Road
  • Barlow Mountain Road from North Street to Route 116
  • Route 116 from Barlow Mountain Road to Craigmoor
  • Craigmoor Road (entire road)

Anticipated completion date is Friday Aug. 16.

The schedule is subject to change pending the weather.