Town of Ridgefield Milling And Paving Schedule For Aug. 5-12
Here's where you can expect to find delays next week…
RIDGEFIELD, CT — Here's the schedule of milling and paving on local roads Aug. 5-12, according to the Town of Ridgefield:
Monday, Aug. 5 Milling Begins:
- Barlow Mountain Road from North Street to Route 116
- Route 116 from Barlow Mountain Road to Craigmoor
- Craigmoor Road (entire road)
Thursday, Aug. 8 Milling Begins:
- Ligi’s Way
- Farmingville Road
Monday, Aug. 12 Paving Begins:
- Ligi’s Way
- Farmingville Road
- Barlow Mountain Road from North Street to Route 116
- Route 116 from Barlow Mountain Road to Craigmoor
- Craigmoor Road (entire road)
Anticipated completion date is Friday Aug. 16.
The schedule is subject to change pending the weather.