Major Natural Gas Line Replacement Project Slated In Southington

Eversource plans natural gas line upgrades in Southington will take place through December, with weekday construction and road repairs.

SOUTHINGTON, CT — Eversource is planning natural gas infrastructure improvements along Woodruff Street in Southington, with construction scheduled to begin this month and continue through December.

The utility announced the project in a notice dated Nov. 6, outlining plans to replace aging natural gas pipelines with newer plastic piping designed to improve safety and reliability.

The work is part of Eversource's ongoing program to replace older cast-iron and bare-steel natural gas mains throughout its service territory.

Find out what's happening in Southingtonfor free with the latest updates from Patch.

According to the utility, the replacement pipes are designed to withstand harsh underground conditions while helping reduce emissions.

Construction Schedule And Traffic Impacts

Find out what's happening in Southingtonfor free with the latest updates from Patch.

Construction on Woodruff Street is scheduled to take place primarily Monday through Friday, from 7 a.m. to 4 p.m.

Eversource said Saturday or nighttime work may occasionally be necessary to keep the project on schedule or meet local requirements.

The work is weather-dependent, and construction schedules may change.

Residents and motorists should expect construction crews and equipment in the area and are encouraged to use caution when traveling through work zones.

Eversource said it will work to minimize disruptions and maintain access to driveways, homes, and businesses throughout construction.

Businesses within the construction area are expected to remain open and accessible during the project.

The utility also plans to notify residents in advance when work is scheduled on their streets.

Gas Service Lines And Meters May Be Replaced

In addition to replacing underground gas mains, Eversource may replace existing natural gas service lines connecting customers' homes to the distribution system.

The work could include installing new plastic service lines, replacing gas meters, and installing updated equipment.

For properties with indoor gas meters, the project may also involve relocating meters and regulators outside.

According to Eversource, outdoor meters allow utility workers to conduct inspections without entering homes and provide quicker access for emergency responders.

Some service line replacement work may require temporary interruptions to natural gas service.

After completing the work, crews will restore gas service, relight natural gas appliances, and perform safety checks.

Eversource said it will contact affected customers to schedule appointments before beginning work on their properties.

The utility emphasized that workers may need access to homes to inspect existing service lines before certain phases of construction can proceed.

Road And Sidewalk Restoration

Eversource said it is responsible for restoring roadways, curbs, sidewalks and other paved surfaces affected by its construction activities.

Areas disturbed during the project will initially receive temporary repairs to allow the ground to settle.

Permanent road restoration is generally scheduled six to nine months after construction is completed.

The utility said permanent paving typically takes place from late spring through early fall, when weather conditions are more favorable for asphalt work.

Restoration may include pavement milling, resurfacing and repairs to sidewalks or curbs.

The extent of restoration will depend on the construction work performed and agreements between Eversource and the municipality.

Eversource said it will maintain temporary trench repairs until permanent restoration is completed.

Contact Information

Residents with questions or concerns about the Woodruff Street project can contact Eversource construction partner Kathleen Daly at 855-645-2427.

Representatives are available Monday through Friday, from 8 a.m. to 4:30 p.m.

Eversource Gas Supervisor John Folger is also identified in the construction notice as a project contact.

The utility said employees, contractors, and field representatives carry identification and will provide it upon request.

The project is identified as Eversource Project No. 26C709.