SUFFIELD, CT — Buying an existing medical office building could offer Suffield a cheaper home for school administrators as officials look for savings in the proposed middle school project.
Superintendent Matt Dunbar discussed a property near McAlister Intermediate School at the Nov. 5 selectmen’s meeting, according to the meeting minutes. He said that alternative could roughly halve central-office costs, with eligible expenses potentially qualifying for state reimbursement.
Those savings would apply to administrative space, rather than the entire school project. The minutes identify neither an address nor a purchase price and record no purchase approval.
Find out what's happening in Suffieldfor free with the latest updates from Patch.
Permanent Building Commission Chairman Kevin Goff considered the building a viable possibility but called for a space plan and renovation estimates. Parking and purchase timing also need review.
The discussion follows earlier debate over the school and firehouse proposals’ tax impact. Selectman Kathy Dunai questioned costs and sought comparisons of renovation and replacement. Kathleen Harrington suggested considering the school first and replacing the firehouse later.
Find out what's happening in Suffieldfor free with the latest updates from Patch.
READ MORE:
- Report Details Medical Emergency Before Suffield Head’s Resignation
- Suffield Gym Cites Rising Costs, Falling Membership In Closure
- 5 Things In Suffield: Zoning Hearings, School Board
Why Replace The Middle School?
The existing school at 350 Mountain Road opened in 1964 as a high school. In a Nov. 1 explanation published in The Suffield Observer, Goff cited aging building systems and problems with accessibility, ventilation, acoustics and natural light.
The commission recommended a new school on the same campus, retaining and renovating the auxiliary gym for community use and incorporating central-office improvements. Its preliminary estimate was $128.8 million, with a $65.3 million town share after anticipated state reimbursement.
Goff’s comparison put the town’s estimated share of major capital improvements at $63 million and renovation as new at $73 million. He argued that repairs would leave functional shortcomings and renovation would require years of work around students.
“These figures remain preliminary and will be refined through design and the State reimbursement process,” Goff wrote.
As Patch previously reported, officials have also discussed a lower potential town share based on additional aid. Those reimbursement assumptions remain under review.
More Savings Under Review
On Nov. 5, officials also considered reducing school square footage and reconsidering community gym space. First Selectman Colin Moll stressed affordability; additional school board and finance board input was needed.
The construction assumptions included annual cost increases of 4.5 percent. No final school design or financing plan was approved at that meeting.