The Nuclear Regulatory Commission said in September Millstone fully corrected a February 2011 error - and a similar November 2011 error - and will go back to a regular level of inspection.

This article was written by Waterford Patch Local Editor Paul Petrone.

Tuesday, federal regulators announced that Millstone Power Station was no longer getting more scrutiny than what is deemed normal for a power plant after a September inspection where it showed it correctedΒ an issue fromΒ February of 2011.Β 

In February of 2011, the Nuclear Regulatory Commission discovered a β€œwhite finding” – which means a problem that causes a low to moderate safety risk – at Waterford'sΒ Millstone Power Station after an operator turned a dial the wrong way, and increased the power to Unit 2Β instead of cutting it off. In November of 2011, Millstone made a similar mistake, Ronald Bellamy of the NRC said.Β 

Millstone went back, addressed the issue and proved to the NRC in SeptemberΒ that they had indeed corrected the problem, Bellamy said. The power plant’s Unit 2 nuclear reactor was receiving a higher level of scrutiny by the NRC following the incident, but with Millstone proving they have corrected the problem, the NRC will go back to its normal level of inspection, Bellamy said.Β 

β€œThat’s where we want to be as a licensee,” Millstone spokesman Ken Holt said. β€œThat is a reflection of our performance over the last year.” 

ProblemΒ 

In February of 2011, a Unit 2 operator turned a dial the wrong way at the Waterford nuclear power plant, which increased the power of the reactor instead of cutting it off, Nuclear Energy Advisory Council President J.W. β€œBill” Sheehan said Tuesday. Perhaps more troubling, no one at the plant immediatelyΒ realized there was a problem, Sheehan said.Β 

The NRC issued Millstone a β€œwhite finding,” which means the plant made an error that causedΒ a low to moderate risk, and with that finding came additional scrutiny by the NRC. Bellamy said that out of the 104 power plants in the United States, only 16 are dealing with findings of that significance.Β Β 

Millstone took the operators responsible for the error off of their regular duties and trained them on the simulator, Holt said. However, in November of 2011, a similar problem happened again, Bellamy said.Β 

β€œObviously, we missed something in our corrective actions from our first event,” Holt said. β€œWe had to look at our training program.” 

Holt said the training programs were redone with β€œa new focus.” That proved effective, as the power plant demonstrated to the NRC in SeptemberΒ it had fully understood and corrected the mistake, and the regulatory agency went back to its standard level of inspection on Unit 2, Bellamy said.Β 

Overall, it took Millstone more than a year to fix the problem, Bellamy said. James Krafty, the NRC’s Unit 2 Residential Inspector, said that taking more than a year to fix a problemΒ is β€œnot the norm,” as it is longer than usual.Β 

2012 PerformanceΒ 

In 2012, Bellamy said the plant operated without anyΒ notable incidents.Β He said the NRC deemed that for the past year, Dominion operated the plant safely.Β Β 

β€œThey have corrected that finding and transitioned back (to standard operating procedure),” Bellamy said.Β 

Standing operating procedure still comes with many hours of inspection by the NRC. Three NRC inspectors are stationed at the Waterford power plant, and they inspected Millstone forΒ 7,300 in 2012, Bellamy said. Β 