OLD LYME, CT — Construction of the proposed Halls Road sidewalk could begin in April 2028 as Old Lyme officials pursue state approval of a revised route, additional grant funding and potential design changes to reduce construction costs.
The Halls Road Sidewalk Committee reviewed the project's progress during its Nov. 18 meeting, reaching agreement on a 6-foot sidewalk width and discussing engineering challenges near the Lyme Art Association, Huntley Road and Big Y.
Committee Chairman Timothy Griswold reported that the Board of Selectmen voted Nov. 2 to approve the committee's recommendation to modify the proposed sidewalk route.
Under the revised plan, the sidewalk would follow the north side of Halls Road from Lyme Street to the west side of Huntley Road, where it would cross to the south side of Halls Road and continue to Route 156.
First Selectwoman Martha Shoemaker said she contacted Colin Horan of the Connecticut Department of Transportation's Community Connectivity Grant Program to request approval of the modification.
Committee members Robert Antoniac and Chris Kerr questioned whether the revised route would be significantly more expensive than an alternative crossing near the Hideaway restaurant and post office entrances.
Kerr noted that the alternative would involve fewer curb cuts, while Antoniac raised concerns about the expense of realigning the Huntley Road entrance and navigating existing infrastructure near the crosswalk.
Aaron Mortensen, an engineer with Jacobson Engineering, said the additional cost of constructing sidewalks across curb cuts would be relatively limited. Installing two flashing yellow pedestrian lights could cost approximately $25,000, he said.
Mortensen also said the DOT would be unlikely to approve a pedestrian crossing near the Hideaway and post office entrances.
Griswold noted that the committee had unanimously recommended the Huntley Road crossing at its previous meeting and said requesting another change at this stage would be inappropriate.
Mortensen is exploring an alternative sidewalk design near the Lyme Art Association, where construction is expected to be the most expensive portion of the project.
Rather than constructing an elevated sidewalk approximately level with Halls Road, the alternative would follow the property's existing grade toward the parking area, cross a shorter section of the creek using a pedestrian bridge and then rise toward the Florence Griswold Museum property.
Mortensen said the right of way extends approximately 26 feet from the Halls Road curb in that area, providing flexibility in the design.
He expects to present additional information at the committee's December meeting.
Griswold also reported that town officials, Mortensen and a representative of the Lyme Art Association met with Historic District Commission Co-Chair Russell Todd to review engineering surveys and potential pedestrian bridge designs.
Todd appeared supportive of the design and encouraged officials to give the improvements a natural, weathered appearance, according to Griswold.
The Lyme Art Association supports the sidewalk plan and recognizes that construction will affect a portion of its parking area adjacent to Halls Road.
Mortensen expects surveying along the south side of Halls Road between Huntley Road and Route 156 to be completed in early January 2027.
Committee members agreed that the sidewalk should be 6 feet wide rather than the previously discussed 5 feet.
The design also calls for a 3-foot snow shelf.
Members discussed incorporating slight curves into the sidewalk near Big Y, but Mortensen said the available right of way, estimated at approximately 12 feet, would make that impractical.
The right of way narrows to approximately 6 feet near Route 156.
Members also agreed that the Big Y truck entrance should remain wide enough to accommodate tractor-trailers.
The town has an $800,000 grant for the sidewalk project, although officials have not determined how much of the proposed route can be constructed with that funding.
Mortensen said he could provide a preliminary estimate but cautioned that several unresolved design elements would limit its reliability.
Shoemaker said the town could apply for additional funding through the Transportation Rural Improvement Program in March 2027.
The project may also require easements from the Lyme Art Association, the Florence Griswold Museum and the owners of 100 Halls Road.
The DOT must review and approve the final plans before the town can solicit construction bids.
Mortensen estimated that preparatory work could be completed by December 2027, potentially allowing construction to begin in April 2028.
Griswold reported that the committee had an available balance of $245,835.84 at the end of September.
October interest earnings added $745.57, while a $10,651.01 payment to Jacobson Engineering on Nov. 12 reduced the balance to $235,930.40.
The committee also approved its Oct. 21 meeting minutes on a motion by Don Bureau, seconded by Kerr.
Seven committee members attended the Nov. 18 meeting at Memorial Town Hall. There were no public comments.
The meeting adjourned at 7:47 p.m.
Sign up for free local newsletters and alerts for the
The Lymes Patch
Patch.com is the nationwide leader in hyperlocal news.
Visit Patch.com to find your town today.