WETHERSFIELD, CT — The Wethersfield Advisory School Building Committee unanimously approved drawings, specifications and an $8.28 million construction estimate for the first phase of the new Highcrest Elementary School project during its Nov. 9 meeting.
The committee also approved more than $244,000 in professional services invoices and contract expenses, reviewed a proposed construction labor agreement and discussed potential delays in obtaining steel.
Michael Scott of TSKP Studio outlined three major components of the project's first phase:
Committee Chairwoman Emily Zambrello moved to approve the drawings, specifications and construction estimate of $8,283,180. Hazim Korkutovic seconded the motion, which passed 6-0.
Scott also reported that the project had received Planning and Zoning approval, with several remaining items to be addressed administratively.
Henry Boers of Construction Solutions Group reported that the Wethersfield Building Department and an independent third party had completed their review of the first-phase drawings.
Tom Romagnoli of Downes Construction reviewed a proposed project labor agreement between the construction company and the Greater Hartford-New Britain Building Trades.
Two outstanding provisions involve local employment and apprenticeship opportunities for Wethersfield students.
The agreement establishes a goal of having Wethersfield residents account for 25% percent of the project's workforce.
Romagnoli said Downes would make every effort to meet that goal, while acknowledging that it was an ambitious target given the public bidding process.
The agreement also requires that 10 Wethersfield High School students receive an opportunity to participate in a building trades apprenticeship program.
Zambrello asked committee member Jim Reilly to bring the apprenticeship proposal to the Board of Education and determine whether school officials would be interested in a presentation from building trades representatives.
Reilly agreed to raise the matter at the board's next meeting.
No vote approving the labor agreement was recorded.
Committee Vice Chairman Richard Sitnik raised concerns about potential long-term delays in obtaining steel for the construction project.
J. Anderson of Downes Construction said a meeting with a major steel distributor was scheduled for later that week to assess potential delays and determine how to address them.
Anderson also reported that Downes had completed its first-phase construction document estimate and presented a project update to the Highcrest PTO on Nov. 5.
The company received second-phase construction documents from TSKP on Oct. 30 and has begun developing the corresponding budget.
A special building committee meeting may be necessary Dec. 7 to approve second-phase drawings, specifications and budget materials.
Jacob Drive resident Nancy Jainchill questioned the proposed playground surfacing materials and access to an enclosed outdoor area designated for younger students.
Jainchill expressed concern about petroleum-based playground surfaces and suggested engineered wood fiber as an alternative, citing accessibility and safety considerations.
Scott clarified that the enclosed courtyard would be reserved for prekindergarten and kindergarten students and would not have a grass surface.
He said petroleum-based, plastic-based and cork-based playground materials remain under consideration, with the final selection dependent on cost, durability and lifecycle expenses.
Scott said engineered wood fiber requires frequent maintenance and compaction that municipalities may have difficulty maintaining consistently.
Jainchill also questioned why the Parks and Recreation Department would oversee reservations for outdoor spaces.
Zambrello said the superintendent had indicated that the department already manages reservation requests for outdoor space at the existing Highcrest school outside regular school hours.
The committee unanimously approved two invoices and a contract amendment:
Each measure passed 6-0.
The code review expense will be incorporated into CSG's contract to make it eligible for reimbursement, according to discussion at the meeting.
Zambrello reported that the town's Human Resources Department had received a committee member's resignation letter and that a replacement was expected to be appointed by December.
She also plans to work with committee member Katie Kumnick to update the project website and add photographs.
Zambrello will coordinate with the town's social media manager to discuss distributing project updates to residents.
The committee approved its Oct. 26 meeting minutes with several corrections, including additional language documenting members' request for time to review updated construction estimates and drawings before taking action.
The motion passed 6-0.
All six committee members attended the meeting, which was held at the Stillman Building, 127 Hartford Ave.