Middlebury WPCA Approves Sewer Capacity For Southford Road Development, Reviews Pump Station Repairs

Middlebury WPCA approves sewer capacity for a Southford Road project and reviews $60,000 in proposed pump station door replacements.

MIDDLEBURY, CT β€” The Middlebury Water Pollution Control Authority unanimously approved a sewer capacity application for a proposed commercial development at 927 Southford Road during its Nov. 17 meeting, subject to final review by the authority's engineer.

The authority also reviewed plans to replace deteriorating doors at three sewer pump stations, discussed an upcoming monitoring system upgrade and approved its 2027 meeting schedule.

Sewer Capacity Approved For Commercial Development

Kade Courtois, representing the applicant, presented plans for a two-phase commercial development at 927 Southford Road.

Find out what's happening in Woodbury-Middleburyfor free with the latest updates from Patch.

The proposal involves dividing the property into two lots, retrofitting an existing building and constructing additional commercial space.

Courtois said the first phase includes renovating the existing building and connecting it to the sewer system, pending required approvals. The building would then be used as rental property.

Find out what's happening in Woodbury-Middleburyfor free with the latest updates from Patch.

The project also includes proposed industrial flex space.

The applicant presented wastewater capacity calculations based on the property's acreage and proposed uses.

According to the minutes, the first lot contains approximately 3.37 acres, or 3.31 acres excluding wetlands. Using an allocation of 460 gallons per day per acre, the applicant calculated a capacity of 1,522.6 gallons per day.

For the proposed buildings, the applicant calculated wastewater demand of 2,084 gallons per day using Connecticut Public Health Code rates.

The second lot would contain approximately 2.45 acres, or 2.15 acres excluding wetlands. The existing three-bedroom house was assigned a wastewater demand of 450 gallons per day, while proposed industrial flex space was assigned 400 gallons per day.

The applicant requested approximately 2,488 gallons per day of sewer capacity for the entire property.

Town Engineer John Calabrese and another reviewer examined the calculations.

The minutes indicate that the property's overall acreage could support an allocation of approximately 2,507 gallons per day under one calculation and 2,509 gallons per day under another.

Calabrese explained that the first phase requires additional capacity, which would be drawn from the allocation associated with the existing house.

If the applicant needs additional sewer capacity in the future, the project must return to the authority for further review.

Paul Phillips moved to approve the sewer capacity application, subject to final plan review by the WPCA engineer.

Anthony Mancini seconded the motion, which passed unanimously.

Pump Station Door Replacement Could Cost $60,000

WPCA employee Matthew Morytko reported that the authority is evaluating replacement doors at three sewer pump stations.

The project involves nine doors, with an initial estimate of $60,000.

Morytko said he is seeking additional quotes before proceeding.

He reported that the existing door frames appear to be in reasonably good condition and that some repairs may be possible without replacing all the framing.

The work can wait until the authority's January 2027 meeting for further discussion, he said.

The authority did not approve the expenditure during the Nov. 17 meeting.

Sewer Monitoring System Upgrade Nears Completion

Morytko also reported progress on the authority's supervisory control and data acquisition system, commonly known as SCADA.

The system is used to monitor and control wastewater infrastructure.

Morytko said the system should be operational soon, with the remaining work awaiting an electrician.

He also reported that routine maintenance was continuing.

No additional funding or contract approvals were recorded for the SCADA work.

State Bridge Project Not Expected To Affect Sewers

The authority reviewed a Connecticut Department of Transportation project involving replacement of Bridge No. 07059, which carries Interstate 84 over Wooster Brook.

Calabrese said the bridge replacement is not expected to affect Middlebury's sewer system because sewer infrastructure is not located near the work area.

He explained that a deteriorating corrugated metal pipe prompted officials to contact the WPCA to determine whether the project could affect municipal sewer facilities. Calabrese reported that no sewer impacts were anticipated.

The authority took no action on the bridge project.

WPCA Approves 2027 Meeting Schedule

The authority unanimously approved its meeting schedule for 2027.

Chairman Robert Smith introduced the motion, which Mancini seconded.

The authority is scheduled to meet on the third Tuesday of each month at 7:30 p.m. in Room 26 of the Shepardson Community Center at 1172 Whittemore Road. The first meeting of 2027 is scheduled for Jan. 19.

Additional meetings are scheduled for Feb. 16, March 16, April 20, May 18, June 15, July 20, Aug. 17, Sept. 21, Oct. 19, Nov. 16 and Dec. 21. The authority also considered canceling its Dec. 15, 2026, meeting.

Previous Meeting Minutes Approved

The authority unanimously approved its July 21 meeting minutes with two corrections.

One correction clarified that a property was classified as office or building space.

The second corrected a reference to installation of a mini-split heating and cooling system.

Smith moved to approve the corrected minutes, with Phillips seconding.

Meeting Details

Smith called the Nov. 17 meeting to order at 7:30 p.m. at the Shepardson Community Center.

Members present were Smith, Phillips, Mancini and Larkin. Ted Mannello was absent.

Also attending were WPCA attorney Stephanie Cummings of Carmody Law, Morytko, recording clerk Jennifer Rivera and Calabrese.

The meeting adjourned at 7:40 p.m. following a unanimous vote on a motion by Mancini, seconded by Phillips.