Parkway Boulevard To Open In Next Three Or Four Weeks, Oconee County Public Works Director Says

The roadway will allow traffic to flow from Epps Bridge Parkway to the Oconee Connector.

Oconee County expects to open Parkway Boulevard from the Oconee Connector to Kohl’s by the end of May, county Public Works Director Emil Beshara told a meeting of the regional metropolitan transportation planning organization on Wednesday.

Construction on the roadway is “winding down,” Beshara told the group, with work remaining only on such things as pedestrian islands, guardrails, and striping.

The roadway will allow traffic to flow from Epps Bridge Parkway just inside Oconee County at the bridge over McNutt Creek to one of the entrances to Epps Bridge Centre or on to SR Loop 10 and SR 316–or the reverse.

Find out what's happening in Oconeefor free with the latest updates from Patch.

The county decided to spend $3.35 million to build the roadway not as a means of relieving traffic but to open up the area for further commercial development.

None of that development is ready to open, but aerial video of the roadway shows that extensive site preparation for the Phase II expansion of Epps Bridge Centre has been completed.

Find out what's happening in Oconeefor free with the latest updates from Patch.

For more on the story, as well as to watch the aerial video tour of the roadway, go to Oconee County Observations.

Pictured: Future Site Of Epps Bridge Centre Phase II.