Burr Ridge May Claim Back Money After Bid Fiasco
The village spent $550,000 with an architectural firm for a project where bids came in far higher than expected.

BURR RIDGE, IL – Burr Ridge may work to get some of the money it paid an architectural firm for the new Village Hall.
The plan for the building ended last month after bids came in far higher than expected.
After the fiasco, the Village Board terminated its relationship with Oak Brook-based Legat Architects. The village spent more than $550,000 with the firm.
Find out what's happening in Burr Ridgefor free with the latest updates from Patch.
In an aside at Monday's board meeting, Mayor Gary Grasso noted the money spent.
"We did pay Legat a fair amount of money," he said. "Now, there might be some claims to that going forward."
Find out what's happening in Burr Ridgefor free with the latest updates from Patch.
On Tuesday, Patch asked Grasso whether he was referring to a lawsuit or something less formal. He said it was the latter.
"The Village will endeavor to work with Legat on some village concerns," the mayor said in a text message.
Legat has not returned messages for comment.
The village had been planning to build an addition to the 16-year-old police station that would serve as the new Village Hall.
But the low bid ended up being more than $5 million over Legat Architects' estimate of $8.5 million. Many bids were $15 million to $17 million.
Officials suggested Legat misled the village on costs.
The village is selling its 41-year-old Village Hall to the Goddard preschool chain. The village said the structure was in bad shape and too costly to upgrade.
Now, the village is reviewing its options. Since the spring, Village Hall employees have worked at the public works office on Commerce Street.