Politics & Government
Lockport Approves 2 Design Proposals For Utility Improvements
One proposal was for $112,000, the second was for $105,000.
LOCKPORT, IL — The Lockport City Council approved two proposals for designs of planned utility projects in the City, at its Wednesday meeting.
The first proposal, for $112,000, is from Chamlin & Associates for the Archer Avenue, Maryknoll Drive and 151st Street utility corridor.
This project will include the installation of a new lift station at Archer and 151st, according to Council documents. New watermain will also be installed along Archer from Maryknoll to 151st.
Find out what's happening in Homer Glen-Lockportfor free with the latest updates from Patch.
The construction for this project would be done in phases.
"As all of these utilities and utilities City-wide are interconnected, the design should be completed in one phase to ensure optimal functionality for the region," Council documents state.
Find out what's happening in Homer Glen-Lockportfor free with the latest updates from Patch.
The second proposal, also from Chamlin & Associates, was at a cost of $105,000 for the design of the Bruce Road and SOS Children's Village utility improvement project.
This project would also include a new lift station, and new water main.
Council documents note that this project is a candidate for future grant funding, and having the design finished will help improve chances for funding.