CHICAGO, IL — The installation of a tower crane will close a section of Fullerton Avenue starting Monday. The crane will go up at the Belmont Village construction site, and its installation is expected to be completed by Wednesday, weather permitting. Fullerton Avenue will be closed during that time between Orchard and Burling streets.
According to the Lincoln Common website, installation of the lower tier earth retention bracing is nearing completion. Excavation is expected to continue through December.
"Thank you for your continued patience and understanding as we work through these critical first steps of construction," The Belmont Village project construction group posted on the Lincoln Common website.
Find out what's happening in Lincoln Parkfor free with the latest updates from Patch.
Here is the upcoming construction schedule for Belmont Village:
Week of 12/4/17:
Find out what's happening in Lincoln Parkfor free with the latest updates from Patch.
- Excavation
- Erect tower vrane
- Mobilization and beginning of concrete activities
Week of 12/11/17:
- Excavation
- Concrete
- Underground plumbing installation