Revised Meadow Plaza Plan Adds Village Square, Shops Before Hearing
Northbrook's hearing resumes Tuesday with more commercial space, 11 small shops and a proposed public square.
NORTHBROOK, IL — A revised proposal to redevelop Meadow Plaza would add a public square with 11 small business storefronts, increase commercial space and eliminate a planned riverwalk as Northbrook's Plan Commission prepares to resume its public hearing Tuesday.
The changes come after October hearings on Pulte Home Company's proposal to replace the downtown shopping center with 150 condominiums in three six-story buildings and commercial development.
The continued hearing begins at 6 p.m. Tuesday, Nov. 17, at Techny Prairie Activity Center, 180 Anets Drive. According to the village's meeting notice, public testimony and cross-examination will be limited to modifications to the proposed development.
Find out what's happening in Northbrookfor free with the latest updates from Patch.
What Has Changed
The village posted revised plans Nov. 10, saying the applicant made changes in response to comments from residents and Plan Commission members.
Among the most substantial additions is a proposed 0.79-acre Village Square, featuring eight 120-square-foot storefronts and three 200-square-foot storefronts intended for small businesses.
Find out what's happening in Northbrookfor free with the latest updates from Patch.
The square would also include a shared restroom structure with a projection wall and stage, turf-covered open space, seating, string lights and 33 surrounding public parking spaces.
According to the village, Pulte intends to construct the square, storefronts and parking, then donate the land and buildings to Northbrook to operate and maintain. That proposal has not undergone preliminary review by the Village Board.
The village describes the storefronts as a way for startups, artisans and businesses operating from homes or at markets to test a retail location with lower rent and overhead before moving into traditional commercial spaces.
The revised proposal also would:
- Increase one of the two commercial buildings from 5,500 to 7,000 square feet, bringing their combined space to 12,500 square feet, in addition to the small shops.
- Rotate both commercial buildings so they are perpendicular to Cherry Lane.
- Eliminate the proposed riverwalk and remove a smaller parcel adjacent to Village Church from the project.
- Rotate condominium Building Two and place it adjacent to the river, opening visibility into the development from Meadow Road.
- Place all stormwater detention in underground vaults and remove a pond feature, pergola and walking path.
- Provide 13 angled public parking spaces along Meadow Road, replacing 10 proposed parallel spaces, and add 13 spaces near Village Church, including two accessible spaces.
The Keystone Avenue extension into the development would remain a public road, while other previously proposed public roads within the project would become private drive aisles.
The revised narrative, site plan, Village Square concept, subdivision plat and traffic study are available on the village’s Meadow Plaza development webpage.
Opponents Raise Density Questions
Save Downtown Northbrook, a community organization opposing the proposal, renewed its objections Friday, pointing to a correction in the village’s downtown housing figures.
In a written account of the Nov. 10 Village Board meeting, Trustee Matt Cassidy said a consultant had mislabeled housing data. The village had cited 2,818 housing units within one mile of downtown; that figure actually represented units between a half-mile and one mile. Adding the 1,498 units within a half-mile brought the total to 4,316, Cassidy wrote.
Save Downtown Northbrook argues the correction undermines the case for adding more residential density at Meadow Plaza.
"We've said the Pulte plan is the wrong plan in the wrong place," Sanford Stein, an attorney representing the organization, said in its announcement. "Now we know why. More density in massive, tall buildings is not needed. A true town center, anchored by retail and public space is the right plan, for this place."
The village's development information describes additional residents nearby as one strategy for supporting downtown businesses.
What Happens Tuesday
The village expects Tuesday's meeting to include an applicant presentation on the revisions, public testimony, cross-examination, applicant responses and commission deliberation. Commissioners also may direct staff to prepare a draft resolution.
Participants wishing to cross-examine must complete the required form before continued public testimony begins. Both testimony and cross-examination will concern changes to the proposal, according to the notice.
The hearing began Oct. 6 and continued through sessions Oct. 20 and 21. The Plan Commission makes a recommendation; the Village Board retains final approval authority.
The meeting will be livestreamed through the village's Facebook page, meeting archive portal and YouTube channel.