City Of Ames: 13th Street Reconstruction Work Shifts Traffic To South Lanes Beginning Wednesday
All traffic on 13th Street between Burnett and Duff avenues will be shifted to single-lane traffic in both directions on the newly const ...
10/26/2021 8:00 AM
All traffic on 13th Street between Burnett and Duff avenues will be shifted to single-lane traffic in both directions on the newly constructed south (eastbound) two lanes beginning Wednesday, Oct. 27, weather permitting. The north (westbound) two lanes of 13th Street between Burnett and Duff avenues will be closed to begin removal and reconstruction of these lanes. This stage of the project will also include the phased construction of the entrance to Fire Station No. 1 on 13th Street.
Find out what's happening in Amesfor free with the latest updates from Patch.
Access to Burnett, Kellogg, and Douglas avenues north of 13th Street will also be closed, but driveway access to McFarland Clinic and Mary Greeley Medical Center from 13th Street will be open. Anticipated duration to complete reconstruction during this phase of the project is four weeks.
The City of Ames has contracted with Con-Struct to complete this project, which includes the reconstruction of 13th Street from Wilson to Duff avenues. In addition to new concrete street pavement, the 13th Street project also includes storm and sanitary sewer improvements, water main replacement, residential water transfers, and Americans with Disabilities Act (ADA) sidewalk ramp improvements.
Find out what's happening in Amesfor free with the latest updates from Patch.
The project is being completed in five phases to allow emergency vehicles access to and from the Ames Fire Station at 1300 Burnett Ave. At all times, one lane of 13th Street in each direction will remain open to traffic. However, access to side streets will be restricted for safety reasons and to ease potential congestion of the construction zone. Construction is anticipated to be completed in late fall 2021. As with all projects, the actual duration will depend on weather conditions.
All are encouraged to take note of this construction activity in the area and allow extra travel time as delays will occur. Please use alternative routes if available. As always, caution should be exercised when traveling through the construction area.
For more information, contact Dean Sayre, Civil Engineer II, at dean.sayre@cityofames.org or 515.239.5277. For general construction updates, go to www.CityOfAmes.org/Construction