Rte. 2, Crosby's Corner Construction Schedule

Here's a look at the next two weeks of work at Crosby's Corner.

From the Massachusetts Department of Transportation.

Boston MA – The Massachusetts Department of Transportation released the following two-week look ahead schedule for the Route 2/Crosby’s Corner Reconstruction project:

Construction period: October 17, 2016, to October 29, 2016.

Find out what's happening in Concordfor free with the latest updates from Patch.

Daily Lane Closures Eastbound and Westbound will be deployed in work zones along Route 2.

Typical Hours for Lane Closures – Eastbound: 9:30 a.m. (as traffic allows) – 5:30 a.m.; Westbound:6:30 a.m. – 2:30 p.m.

Find out what's happening in Concordfor free with the latest updates from Patch.

All scheduled work could be extended or delayed due to inclement weather.

Night Work:

Route 2, Ramps and Crosby’s Corner:

· Night work tentatively scheduled for Sunday night October 16, through Thursday nightOctober 20. Work hours will occur between the hours of 8:00 p.m., and 5:00 a.m. This work will consist of grinding recessed areas in the new pavement and then applying thermoplastic pavement markings in these recessed areas.

Day Work:

Service Roads:

· Continue construction of the end of Old Cambridge Turnpike.

· Place topsoil, seed and landscape plantings at the end of Old Cambridge Turnpike.

· Install remaining Wood Board Fence at the end Old Cambridge Turnpike.

· Install Emergency Automated Gates at Horses Crossing and Red Maple Lane.

· Plant new trees and bushes.