Falmouth Onshore High Voltage 1200 MW Cables Study

ISO-New England Nov 15, 2023 Planning Advisory Committee

Picture of Covell's Beach in Barnstable onshore cable construction
Picture of Covell's Beach in Barnstable onshore cable construction (Image Credit: Frank Haggerty )

Offshore wind would like to route 1200 megawatts of buried power through the Town of Falmouth to off-cape locations.

Note# (To put the 1200 megawatts in perspective the total output of the Pilgrim nuclear plant was 680 megawatts.)

A study will be done by ISO New England to determine how the project will move forward.

Find out what's happening in Falmouthfor free with the latest updates from Patch.

The offshore wind company proposes placing buried multiple high-voltage direct current cables through residential locations in the Town of Falmouth.

A six-acre HVDC electric substation in Falmouth is included in the offshore-to-onshore proposal.

Find out what's happening in Falmouthfor free with the latest updates from Patch.

Note# Onshore Substation – The onshore substation transforms the power to grid voltage, stepping up to 345 kV.

According to an April 27, 2023, local news story: The offshore wind company's power needs exceed the current power grid capacity thus wind company must pay for the upgrades.
ISO New England will conduct a feasibility study. The upgrade will be completed by 2028.

-------------------------------------------
See the information and link below:
Local System Plan 2023
Transmission Owner Planning Advisory Committee
November 15, 2023
-----------------------------------------------------------------------------------------------------------------------------------------

ISO New England Information :
Study Identification: ES-23-LSP043

Need: Local Reliability

Project: New Bourne to Falmouth Tap 115kV Line
Solution Description: Install a new 115-kV transmission line between Bourne and Falmouth Tap substation to mitigate Consequential Load Loss violations under N-1-1 conditions.

ISD projected: 2028 Proposed

Cost To Be Determined
https://www.iso-ne.com/static-assets/documents/100005/2023_11_15_topac_lsp_eversource_presentation.pdf