Falmouth Onshore High Voltage 1200 MW Cables Study
ISO-New England Nov 15, 2023 Planning Advisory Committee

Offshore wind would like to route 1200 megawatts of buried power through the Town of Falmouth to off-cape locations.
Note# (To put the 1200 megawatts in perspective the total output of the Pilgrim nuclear plant was 680 megawatts.)
A study will be done by ISO New England to determine how the project will move forward.
Find out what's happening in Falmouthfor free with the latest updates from Patch.
The offshore wind company proposes placing buried multiple high-voltage direct current cables through residential locations in the Town of Falmouth.
A six-acre HVDC electric substation in Falmouth is included in the offshore-to-onshore proposal.
Find out what's happening in Falmouthfor free with the latest updates from Patch.
According to an April 27, 2023, local news story: The offshore wind company's power needs exceed the current power grid capacity thus wind company must pay for the upgrades.
ISO New England will conduct a feasibility study. The upgrade will be completed by 2028.
-------------------------------------------
See the information and link below:
Local System Plan 2023
Transmission Owner Planning Advisory Committee
November 15, 2023
-----------------------------------------------------------------------------------------------------------------------------------------
ISO New England Information :
Study Identification: ES-23-LSP043
Need: Local Reliability
Project: New Bourne to Falmouth Tap 115kV Line
Solution Description: Install a new 115-kV transmission line between Bourne and Falmouth Tap substation to mitigate Consequential Load Loss violations under N-1-1 conditions.
ISD projected: 2028 Proposed
Cost To Be Determined
https://www.iso-ne.com/static-assets/documents/100005/2023_11_15_topac_lsp_eversource_presentation.pdf