Falmouth Turbine # 2 Demolition Probability Oct 5, 2022
Wind turbine # 2 is estimated to be taken down Wednesday, October 5, 2022

The Massachusetts Superior Court in 2017 ordered that the decision of the Falmouth Zoning Board of Appeals be affirmed that the operation of Wind # 1 and Wind # 2 constitute a nuisance and that the Town of Falmouth ceases and desists operation of the wind turbines. They have not operated since 2017.
A contractor has been hired to dismantle and/or demolish both town-owned megawatt wind turbines.
Falmouth Wind # 1 was demolished on September 26, 2022..
Find out what's happening in Falmouthfor free with the latest updates from Patch.
The probable date for dismantling Falmouth Wind # 2 is Wednesday, October 5, 2022
Falmouth Wind Turbine # 1 Demolition September 26, 2022