Falmouth Wind Turbine Removal Request For Proposal April 2019
Falmouth Town Manager Julian Suso plans to issue RFP, request for proposal for town's 2 wind turbines at the wastewater plant site in April

Falmouth Town Manager Julian Suso plans to issue RFP, request for proposal for town’s 2 wind turbines at the wastewater plant site in April 2019.
RFP to lease property outside Falmouth or sell the 110-decibel turbines. The neighbors describe the noise as torture.
Barnstable Superior Court Judge Cornelius Moriarty issued the order to shut down Falmouth's Wind 1 and Wind 2 on June 20, 2017. The Massachusetts Appellate Court in the commonwealth has affirmed the decision.
Find out what's happening in Falmouthfor free with the latest updates from Patch.
The Town of Falmouth had known prior to construction the Vestas V-82 type 1.65 megawatt wind turbines each produced a chest pounding 110 decibels of noise each. A hard rock band playing 24/7 equals 110 decibels.
Vestas Wind Company 110 Decibel Noise Warning Prior To Construction
Find out what's happening in Falmouthfor free with the latest updates from Patch.
August 3, 2010
WasteWater Superintendent
Town of Falmouth Public Works
59 Town Hall Square Falmouth, MA 02540
RE: Falmouth WWTF Wind Energy Facility II "Wind II", Falmouth, MA
Contract No. #3297
The Town has previously ( before August of 2010 ) been provided with the Octave Band Data / Sound performance for the V82 turbine. This shows that the turbine normally operates at 103.2dB but the manufacturer has also stated that it may produce up to 110dB under certain circumstances.