Construction is underway at Hingham High School.
The baseball field has been dug up and the bleachers have been demolished.
Field Construction Phasing Schedule:
Union St. pipe, buffer planting, buffer fencing, bleacher demo: Final completion, July 10.
Game field & Interior fence:Final completion, September 15.
Game field Bleachers: Final completion, October 1.
Site lighting, athletic lighting, perimeter fencing: Final completion, October 31.
Baseball Field, Softball Field:Final completion, October 31.
South Parking Lot, access drive, parking, central walkway: Final completion, September 1.