Bids for Mansfield Public Safety-DPW Complex Under Estimates
Three bids were received for the project.

MANSFIELD, MA — Bids for Mansfield's new public safety-DPW complex were lower than expected, town officials said.
The three bids submitted came in at $27.4 million, $28.4 million, and the low of $27.2 million from Boston Building and Bridge Corp. The low bid is about $600,000-700,000 lower than expected, according to the Sun Chronicle.
Mike Ahern, who is the project manager, said the costs include the new traffic light near the complex.
Find out what's happening in Mansfieldfor free with the latest updates from Patch.
Including $9.5 million in soft costs and $1.8 million reserved in contingencies, the total cost of the project is about $35 million, the amount approved at Town Meeting.
The project is expected to take two years and eight months to finish.