Business & Tech

VIDEO: Newburyport/Rockport Line Not So Fine

Commmuter trains were late more than 40 percent of the time in January on the Newburyport/Rockport Line.

The Newburyport/Rockport Line tried the patience of Swampscott commuters in January and part of February.

In January more than 40 percent of the line's commuter trains were late. A year ago less than 12 percent of the line's trains were late.

A Massachusetts Bay Railroad Company spokesman says stormy weather hurt the line's ontime performance. Frozen switches and brakes, an aging fleet and issues with the Beverly drawbridge  contributed to the lateness, said Tom Halkin of Mills & Company, a public relations company that handles media requests for the MBCR.

Find out what's happening in Swampscottfor free with the latest updates from Patch.

The MBCR operates the Massachusetts Bay Transportation Authority's commuter rail service.

Changes to the Newburyport/Rockport line are on the way. These include repairs to the drawbridge and a reduced schedule during major storms.

Find out what's happening in Swampscottfor free with the latest updates from Patch.

Commuters  hope the changes produce results.

Being unable to get to work on time is stressful especially when jobs are hard to come by.

Here's an interview with Tom Halkin of Mills & Company.

What was the on-time performance for the Newburyport/Rockport line in January? How does this compare to previous years and to other months during this winter?

The system-wide OTP for January, 2011 was 72%. OTP for the Newburyport/Rockport Line in January was 59%.

Last January system-wide OTP was 85% and Newburyport/Rockport OTP was 87.5% 

What were the problems? Why

45% of all delays in January were directly related to weather. The impact of running service in harsh winter conditions also took a toll on an aging fleet (most of the locomotive and coaches in the fleet are 20+ years old) and old infrastructure. The main issues were frozen switches (ice stuck in the switch prevents it from closing – has to be cleared manually & each new passing train that kicks snow up/drops ice from the undercarriage and can pack it right back in); signal/gate-crossing malfunctions (caused by excessive road salting); frozen brakes; frozen air-hoses; melting snow shorting out engine circuits on both traction motors (drives the train) and HEP motors (heat, lights, etc.)

On the NBPT/Rockport line, continued issues with the Beverly drawbridge also compounded the delays.

How does a reduced or restricted schedule during major storms help MBCR in getting the trains to run on time?

MBCR has historically experienced a 40% reduction in ridership levels during snow emergencies (people take the day off; work from home, etc.)

A “Snow Emergency Schedule” would ensure reliability, reduce levels of disruption to customers, protect rolling stock from storm-related damage and provide spare equipment by offering adjust levels of service during storms.

If you are running fewer trains on certain days because of major storms, will you run more cars on those trains?

MBCR proposed a snow emergency schedule that would go into effect if the governor declared a snow emergency. Details are still being worked out in conjunction with the MBTA. Nothing is approved yet.

Problems in the Newburyport/Rockport line often seem to be related to the Beverly bridge. What can or is being done to reduce the problems at that spot, as they impact the rest of the line all the way to Boston?

The bridge was built in 1887, and many of the original components are still intact. Maritime law dictates that ocean-going traffic gets the right-of-way and the bridge must open when a watercraft approaches.

The MBTA approved $1.6 million to perform a temporary fix of the bridge by installing a new hydraulic system. Design work is just about complete, and the repair is scheduled to be complete by the end of 2011.

The T is also developing plans to completely replace the bridge, and plan to put that project out to bid in 2012.

How do you plan to get the word out on those days when the commuter rail is going to use a reduced schedule?

Once a “Snow Emergency Schedule” is adopted it will be posted at every station, on MBTA.com and MBCR.net, and when a snow emergency is declared it will be distributed through the T’s and MBCR’s email systems.

Sign boards on the platform, particularly in Swampscott, are frequently wrong and email alerts are also rarely accurate. What are you doing to improve performance and communication?

These are two separate issues:

The platform sign boards are part of the Passenger Train Information System (PTIS). PTIS is an automated, on-bard computer system that generates automated messages inside the coaches and also links real-time information to LED monitors at stations. However, PTIS is just over a year old, and while it has been fully implemented at all stations on the South Side of the system (out of south station), but it is still being rolled-out on the North Side.

Until recently all internet & mobile communications were controlled by the MBTA. Because of the many issues with this system during the snowstorms of January and early February, the MBTA will transfer commuter rail-related communications to the MBCR – the transfer should be completed by mid-March.

MBCR is also aggressively working on implementing a new, additional system for real-time information that will allow all passengers to know where their train is at all times.

Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.