What National Grid Plans to Fix in Waltham
The company last week released a list of potential projects in the Watch City for 2017 and 2018.

WALTHAM, MA – National Grid last week released a list of planned projects in Waltham in 2017 and 2018. The company stressed that its plan is subject to change based on city preference and schedule. In a letter to the city, company representative Grace Sawaya wrote "it is our hope to be one year ahead of the City’s planned Public Works projects."
Below is a look at National Grid's planned projects over the next two years:
2017
| Location | Program | Work Type | Footage |
| 1-80 High St. | Cast Iron | Main Replacement | 1780 ft. |
| 14-20 Gorman Ct. | Cast Iron | Main Replacement | 1065 ft. |
| 17-85 Weston St. | Cast Iron | Main Replacement | 670 ft. |
| 390-675 Main St. | Cast Iron | Main Replacement | 3200 ft. |
| 287-346 School St. | Cast Iron | Main Replacement | 4510 ft. |
| 2-40 Appleton St. | Cast Iron | Main Replacement | 565 ft. |
| 14-56 Harris St. | Cast Iron | Main Replacement | 750 ft. |
| 7-23 Chamberlain Ter. | Cast Iron | Main Replacement | 320 ft. |
2018
| Location | Program | Work Type | Footage |
| 518-1019 Trapelo Rd | Reliability | Main Ret. | 6300 ft. |
Click here for a list of potential city projects that may impact the planned work.