Politics & Government
Downtown Fenton Streetscape Update - May 29
Stay in the know about the Fenton Streetscape 2015 at FentonMomentum.com

For this week and next week, we will continue with installing storm sewer from the Shiawassee River south on LeRoy. The installation of the water services on Mill Street is finishing up. To accommodate the connection of the Storm Sewer northbound traffic on S. LeRoy Street has been shifted to the other side of the street.
As always, please be safe and mindful of your surroundings in the construction zone. If you have questions please free to email streetscape2015@cityoffenton.org.