Hennepin County Will Begin Work On Glenwood Ave From May 18

Crews will mill and pave the corridor the week of May 25, followed by pavement marking installation in early June.

May 12, 2020

Hennepin County will begin work on the Glenwood Ave (County Rd 40) mill and overlay project the week of Monday, May 18, weather permitting. The work will occur between Hwy 100 and Thomas Ave in Minneapolis. Flaggers will be in place to direct vehicles around the work zone.

Find out what's happening in Golden Valleyfor free with the latest updates from Patch.

The week of May 18, crews will remove and replace curbs. Crews will mill and pave the corridor the week of May 25, followed by pavement marking installation in early June.

For more information about the project, go to www.hennepin.us/roadmaintenance.