Here is the latest information about construction of Northfield's new 26,000 square-foot police facility from the city's "Brick by Brick" newsletter:

Special points of interest:
Week of July 15, 2013
• Excavating the site began on Monday July 15, 2013. Heavy rains the weekend before prevented planned blasting of bedrock to make room for footings.
• Grading and excavation continues at the site according to the erosion control plan.
• Meetings with furnishings and fixtures vendors continued this week as well as with vendors associated with security cameras and audio recordings for inter- views and interrogations. All were told to sharpen their pencils!!! 

For updates and other information about the community, join us on Patch, Like us on Facebook and follow Northfield Patch on Twitter.

Find out what's happening in Northfieldfor free with the latest updates from Patch.

The views expressed in this post are the author's own. Want to post on Patch?

More from Northfield