MINNEAPOLIS, MN — As always, Minnesota's summer will feature many big, disruptive construction projects. None will be quite as massive, however, as the one taking over Interstate 35W and Interstate 94 in Minneapolis.
The project — which is expected to last through fall 2021 — will update I-35W infrastructure as the highway's daily traffic continues to climb.
Average daily traffic
Find out what's happening in Southwest Minneapolisfor free with the latest updates from Patch.
- I-35W in 2013: 198,500
- I-35W in 2038: projected to be 257,700
- I-94 in 2013: 243,000 vehicles
- I-94 in 2038: projected to be 288,500
Do the Zipper Merge
When you encounter a construction zone where a lane will be closed, perform the zipper merge. A zipper merge occurs when motorists use both lanes of traffic until reaching the defined merge area, and then alternate in a "zipper" fashion into the open lane.
Here is a complete list of the closures and detours schedule for summer 2018:
Upcoming
7 p.m. Fri, May 4 to 5 a.m. Mon, May 7
Find out what's happening in Southwest Minneapolisfor free with the latest updates from Patch.
- Portland Ave. will be closed from 15th St. to 31st St.
- Detour: Chicago Ave.
- Note: There will be no parking in place. Expect some construction noise throughout the daytime and nighttime.
Mon, May 7 through mid-July
- 4th Ave. will be closed between 12th St. and 14th St.
Ramp closures
Mon, May 7 through mid-July
- 12th St to SB I-35W will be closed to single occupancy vehicles
- Detour: Marquette Ave. to 10th St. to 4th Ave.
Mid-June through fall 2018
- Access to downtown from NB I-35W to 11th St/5th Ave. S/E. Grant St. will be closed
- Detour: 3rd St. (exit 17C)
- Note: When access into downtown reopens from NB I-35W, there will only be one northbound lane available to allow for ongoing construction in the area. Motorists are encouraged to use alternate routes or use transit to travel in/out of downtown.
Mid-June through fall 2021
- Access out of downtown (from 12th St./4th Ave.) to SB I-35W will be closed
- Detour: 3rd Ave. in downtown to 4th St.
Bridge closures
March 2 through early August
- 38th St. bridge is closed over I-35W
- EB detour: Nicollet Ave. to 36th St. to 3rd Ave. S
- WB detour: 3rd Ave. S to 35th St. to Nicollet Ave.
- Bicycle Detour: 1st Ave. S (NB)/Blaisdell Ave. (SB) to 40th St. pedestrian bridge to 3rd Ave. S
- Pedestrian detour: 1st Ave. S to 40th St. pedestrian bridge to 3rd Ave. S
- View map for all 38th St. bridge detours (PDF)
Sept. 18, 2017 through summer 2018
- The Franklin Ave. bridge is closed over I-35W
- WB Detour: Portland Ave. to 26th St. to 3rd Ave.
- EB Detour: Nicollet Ave. to 28th St. to Park Ave.
- Pedestrian Detour: Use 24th St. pedestrian bridge
- View map for all Franklin Ave. bridge detours (PDF)
Lane closures
April 13 through mid-June
- The left lane on NB I-35W is closed from 26th St. into downtown Minneapolis
Ramp closures
April 23 to mid-June
- WB I-94 to 11th St. will be closed
March 2 through fall 2021
- 36th St. to SB I-35W is closed
Aug. 24, 2017 through fall 2021
- 5th Ave. S to NB I-35W is closed
Aug. 24, 2017 through 2018
- 5th Ave. S to EB I-94 is closed
Additional closures
March 2 to early August
- Intersections of Stevens Ave. and Second Ave. S between 37th St. and 38th St. are closed
Image via Minnesota Department of Transportation
Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.