Project Update On Wright County's CSAH 19 And 38 Project
The intersection is expected to be reopened approximately on October 19 – depending on weather conditions over the next three weeks.
September 23, 2020
On Monday, Sept. 21, the contractor for the project closed the intersection of Hwy. 38 and MacIver Avenue to construct a roundabout. The intersection is expected to be reopened approximately Monday, Oct. 19 – depending on weather conditions over the next three weeks.
Find out what's happening in St. Michaelfor free with the latest updates from Patch.
A detour for through traffic will be provided along Hwy. 19 to Hwy. 37 to Hwy 38. Local residents living between MacIver Avenue and Hwy. 19 will have access utilizing city streets, such as 67th, 69th, 73rd and 80th Streets off of Hwy. 19, depending on whether they north or south of Hwy. 38. Access for busses and emergency vehicles will be maintained on Hwy. 38 at Lambert Avenue, Large Avenue and Lasalle Circle.
For an overview of the entire project, click here: https://static1.squarespace.com/static/5b60665a506fbe8de7ce7ec7/t/5e8f7e2102b8fa04beb1d01b/1586462275137/Construction+Handout.pdf
Find out what's happening in St. Michaelfor free with the latest updates from Patch.
This press release was produced by the Wright County Government. The views expressed here are the author’s own.