Brentwood Bound Construction Update For August 12

L. Keeley installation of sanitary sewer structures located adjacent to Mary Avenue.

July 29, 2021

Construction work anticipated in the next two weeks on the Brentwood Bound Plan:

Find out what's happening in Maplewood-Brentwoodfor free with the latest updates from Patch.

Flood Mitigation Phase 1

  • L. Keeley installation of sewer junction chambers and tie-in of the new 72” sewer
  • L. Keeley installation of sanitary sewer structures located adjacent to Mary Avenue
  • L. Keeley earthmoving and soils export
  • L. Keeley 24-hour bypass pumping of the existing horseshoe sewer
  • Demolition Phase 1C

    Find out what's happening in Maplewood-Brentwoodfor free with the latest updates from Patch.

  • Marschel Wrecking remaining utility disconnects at 8000 Manchester Road (Frederic Roofing)
  • Marschel Wrecking HHW removal at 8000 Manchester Road (Frederic Roofing)
  • Marschel Wrecking demolition of 8000 Manchester Road (Frederic Roofing)
  • Site Cameras

    See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.

    Learn more about Brentwood Bound at www.BrentwoodBound.org.