Las Vegas Raiders Update: Stadium Construction Should Be Done In June 2020
The Las Vegas Stadium Authority released a draft timeline ahead of their meeting later this week.

If all goes according to plan, the Las Vegas Raiders will have a solid three months to move in and get used to their new home before the start of the 2020 season. That's according to a draft timeline released Monday by the Las Vegas Stadium Authority as part of the agenda for their meeting later this week.
According to the timeline, work on the 65,000-seat stadium will begin in December, followed by bonds being issued in January.
The actual construction will start that month as well. The timeline anticipates that construction will take 390months giving the team a solid three months to move in before opening day.
Find out what's happening in Las Vegasfor free with the latest updates from Patch.
The Raiders closed on the 62.5 acres where the stadium will be built earlier this month. They are paying $775 million for the property.
(Subscribe to local news alerts on Patch).
Find out what's happening in Las Vegasfor free with the latest updates from Patch.
The timeline also lays out a series of approvals that are needed for the project to keeping moving forward including Clark County's High-Impact Project review, which includes detailed examinations of pretty much everything related to the project including parking, utilities, and impact on the airport.
You can read the timeline here.